Showcase — Completed Works

Rollup last refreshed: 2026-09-08 07:02:23.162126
to
to
Reset filters
Scope
Works completed
358
Sanctioned (pure scheme)
₹4.89 Cr
Expenditure since inception
₹4.41 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
19 works
₹1.08 Cr sanctioned
₹90.95 L spent (84%)
02
Renovation of traditional water bodies
5 works
₹55.74 L sanctioned
₹55.10 L spent (99%)
03
Plantation
23 works
₹39.79 L sanctioned
₹15.75 L spent (40%)
04
Construction of Check Dam/Stop Dam
28 works
₹31.86 L sanctioned
₹33.16 L spent (104%)
05
Constr of Cement Concrete Roads
24 works
₹29.45 L sanctioned
₹29.15 L spent (99%)
06
Land Development
44 works
₹28.16 L sanctioned
₹29.48 L spent (105%)
07
Farm Pond
21 works
₹21.84 L sanctioned
₹21.44 L spent (98%)
08
Construction of Percolation Tank
3 works
₹21.81 L sanctioned
₹21.03 L spent (96%)
09
Rural Housing
118 works
₹21.33 L sanctioned
₹20.98 L spent (98%)
10
Construction of Road and Culvert
4 works
₹19.61 L sanctioned
₹20.57 L spent (105%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 118 0.21 0.21
98%
2 Land Development 44 0.28 0.29
105%
3 Construction of Check Dam/Stop Dam 28 0.32 0.33
104%
4 Constr of Cement Concrete Roads 24 0.29 0.29
99%
5 Plantation 23 0.40 0.16
40%
6 Farm Pond 21 0.22 0.21
98%
7 Construction of Trench 19 1.08 0.91
85%
8 Construction of Toilets 18 0.03 0.03
96%
9 Cattle Shed 8 0.04 0.04
97%
10 Well Recharge 7 0.06 0.05
76%
11 Goat Shelter 6 0.03 0.03
97%
12 Renovation of traditional water bodies 5 0.56 0.55
99%
13 Repair & maint of Pond/ Tank 4 0.15 0.15
95%
14 Construction of Tank 4 0.17 0.16
95%
15 Construction of Road and Culvert 4 0.20 0.21
105%
16 Construction of Bund 4 0.12 0.12
94%
17 Construction of Play field 3 0.11 0.10
89%
18 Construction of Percolation Tank 3 0.22 0.21
96%
19 Repair & Maint of Check Dam/Stop Dam 2 0.11 0.10
96%
20 Underground Dyke for Ground Water Recharge 2 0.02 0.02
92%
21 Repair & maint of Road 2 0.01 0.01
98%
22 Bio-Fertilizer 1 0.02 0.02
98%
23 Construction of Crematorium 1 0.02 0.02
100%
24 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.02 0.02
85%
25 Construction of Well 1 0.02 0.02
95%
26 Constr of Compound wall 1 0.01 0.01
98%
27 Repair & maint of Percolation Tank 1 0.04 0.04
90%
28 Boulder Check/Gully Plug 1 0.04 0.03
87%
29 Solid and Liquid Waste Management 1 0.01 0.01
98%
30 Terracing 1 0.09 0.08
88%
Total 358 4.89 4.41
All 30 rows (zero-value rows hidden) ⇩ Export to Excel