MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-03 07:03:16.173614
to
to
Reset filters
Scope
Works completed
733
Sanctioned (pure scheme)
₹9.27 Cr
Expenditure since inception
₹7.31 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
26 works
₹1.74 Cr sanctioned
₹1.30 Cr spent (75%)
02
Construction of Bund
78 works
₹1.56 Cr sanctioned
₹1.28 Cr spent (82%)
03
Construction of Check Dam/Stop Dam
25 works
₹1.00 Cr sanctioned
₹56.87 L spent (57%)
04
Land Development
56 works
₹67.85 L sanctioned
₹55.29 L spent (81%)
05
Rural Housing
356 works
₹65.92 L sanctioned
₹65.88 L spent (100%)
06
Renovation of traditional water bodies
6 works
₹51.08 L sanctioned
₹31.44 L spent (62%)
07
Construction of Canal
4 works
₹42.58 L sanctioned
₹42.00 L spent (99%)
08
Works for Flood Control and Protection
4 works
₹40.56 L sanctioned
₹40.82 L spent (101%)
09
Plantation
10 works
₹34.77 L sanctioned
₹18.54 L spent (53%)
10
Constr of Cement Concrete Roads
23 works
₹29.59 L sanctioned
₹17.82 L spent (60%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. District Completed Sanctioned Expenditure Exp. %
1 BALAGHAT 733 9.27 7.31
79%
Total 733 9.27 7.31
All 1 rows (zero-value rows hidden) ⇩ Export to Excel