Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
714
Sanctioned (pure scheme)
₹9.64 Cr
Expenditure since inception
₹5.01 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Land Development
70 works
₹5.49 Cr sanctioned
₹45.37 L spent (8%)
02
Rural Housing
318 works
₹59.83 L sanctioned
₹59.76 L spent (100%)
03
Construction of Road and Culvert
21 works
₹46.43 L sanctioned
₹60.21 L spent (130%)
04
Farm Pond
11 works
₹41.05 L sanctioned
₹37.11 L spent (90%)
05
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
6 works
₹40.22 L sanctioned
₹17.84 L spent (44%)
06
Construction of Check Dam/Stop Dam
57 works
₹33.82 L sanctioned
₹1.14 Cr spent (337%)
07
Constr of Cement Concrete Roads
65 works
₹28.50 L sanctioned
₹24.96 L spent (88%)
08
Construction of Spur
4 works
₹27.15 L sanctioned
₹23.81 L spent (88%)
09
Construction of Percolation Tank
4 works
₹25.07 L sanctioned
₹20.90 L spent (83%)
10
Construction of Tank
2 works
₹19.07 L sanctioned
₹18.85 L spent (99%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 318 0.60 0.60
100%
2 Construction of Toilets 70 0.07 0.06
92%
3 Land Development 70 5.49 0.45
8%
4 Constr of Cement Concrete Roads 65 0.29 0.25
88%
5 Construction of Check Dam/Stop Dam 57 0.34 1.14
337%
6 Construction of Road and Culvert 21 0.46 0.60
130%
7 Construction of Bund 19 0.13 0.11
81%
8 Construction of NADEP/Vermi Compost Pit 19 0.03 0.02
87%
9 Solid and Liquid Waste Management 18 0.03 0.02
96%
10 Farm Pond 11 0.41 0.37
90%
11 Plantation 11 0.14 0.09
66%
12 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 6 0.40 0.18
44%
13 Construction of Spur 4 0.27 0.24
88%
14 Construction of Well 4 0.08 0.04
54%
15 Construction of Percolation Tank 4 0.25 0.21
83%
16 Cattle Shed 3 0.03 0.03
98%
17 Terracing 3 0.18 0.15
82%
18 Construction of Tank 2 0.19 0.19
99%
19 Community Sanitary Complex 2 0.01 0.01
100%
20 Construction of Canal 1 0.02 0.02
88%
21 Construction of building/workshed for SHG 1 0.05 0.04
96%
22 Constr of Food Grain storage 1 0.10 0.10
99%
23 Constr of Compound wall 1 0.00 0.00
99%
24 Constr of Aganwadi 1 0.05 0.05
100%
25 Construction of Trench 1 0.00 0.00
41%
26 Construction of Crematorium 1 0.02 0.02
99%
Total 714 9.64 5.01