Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
833
Sanctioned (pure scheme)
₹5.50 Cr
Expenditure since inception
₹4.33 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
16 works
₹1.02 Cr sanctioned
₹82.39 L spent (81%)
02
Plantation
20 works
₹97.29 L sanctioned
₹38.20 L spent (39%)
03
Rural Housing
433 works
₹76.73 L sanctioned
₹76.82 L spent (100%)
04
Land Development
98 works
₹56.96 L sanctioned
₹46.43 L spent (82%)
05
Construction of Check Dam/Stop Dam
48 works
₹53.12 L sanctioned
₹47.22 L spent (89%)
06
Construction of Well
30 works
₹39.76 L sanctioned
₹33.80 L spent (85%)
07
Constr of Cement Concrete Roads
25 works
₹24.28 L sanctioned
₹31.08 L spent (128%)
08
Construction of Trench
4 works
₹20.63 L sanctioned
₹18.55 L spent (90%)
09
Constr of Compound wall
3 works
₹17.42 L sanctioned
₹16.17 L spent (93%)
10
Boulder Check/Gully Plug
5 works
₹15.29 L sanctioned
₹5.98 L spent (39%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 433 0.77 0.77
100%
2 Land Development 98 0.57 0.46
82%
3 Construction of Check Dam/Stop Dam 48 0.53 0.47
89%
4 Construction of Toilets 33 0.01 0.01
52%
5 Farm Pond 30 0.13 0.09
64%
6 Construction of Well 30 0.40 0.34
85%
7 Construction of NADEP/Vermi Compost Pit 28 0.04 0.03
86%
8 Constr of Cement Concrete Roads 25 0.24 0.31
128%
9 Plantation 20 0.97 0.38
39%
10 Solid and Liquid Waste Management 20 0.01 0.01
54%
11 Construction of Road and Culvert 16 1.02 0.82
81%
12 Constr of Kitchen Shed 11 0.01 0.00
18%
13 Boulder Check/Gully Plug 5 0.15 0.06
39%
14 Construction of Bund 5 0.05 0.02
32%
15 Repair & Maint of Community infrastructure 4 0.02 0.02
99%
16 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 4 0.03 0.03
101%
17 Constr of Food Grain storage 4 0.00 0.03
0%
18 Construction of Trench 4 0.21 0.19
90%
19 Construction of Crematorium 3 0.05 0.04
70%
20 Culvert 3 0.03 0.03
130%
21 Constr of Compound wall 3 0.17 0.16
93%
22 Community Sanitary Complex 2 0.01 0.01
85%
23 Poultry Shelter 1 0.00 0.00
66%
24 Repair & maint of Pond/ Tank 1 0.04 0.03
72%
25 Cattle Shed 1 0.01 0.01
99%
26 Construction of Play field 1 0.02 0.01
75%
Total 833 5.50 4.33
All 26 rows (zero-value rows hidden) ⇩ Export to Excel