Showcase — Completed Works

Rollup last refreshed: 2026-09-18 07:04:14.05263
to
to
Reset filters
Scope
Works completed
769
Sanctioned (pure scheme)
₹8.71 Cr
Expenditure since inception
₹6.81 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
27 works
₹2.31 Cr sanctioned
₹1.95 Cr spent (84%)
02
Construction of Road and Culvert
30 works
₹1.95 Cr sanctioned
₹1.13 Cr spent (58%)
03
Construction of Check Dam/Stop Dam
60 works
₹1.08 Cr sanctioned
₹72.63 L spent (67%)
04
Rural Housing
430 works
₹83.81 L sanctioned
₹81.61 L spent (97%)
05
Construction of Well
44 works
₹66.25 L sanctioned
₹59.27 L spent (89%)
06
Constr of Cement Concrete Roads
26 works
₹43.07 L sanctioned
₹50.63 L spent (118%)
07
Plantation
16 works
₹36.72 L sanctioned
₹5.69 L spent (15%)
08
Farm Pond
10 works
₹20.88 L sanctioned
₹16.15 L spent (77%)
09
Constr of Aganwadi
3 works
₹18.58 L sanctioned
₹17.17 L spent (92%)
10
Construction of Percolation Tank
4 works
₹10.48 L sanctioned
₹6.75 L spent (64%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 430 0.84 0.82
97%
2 Construction of Check Dam/Stop Dam 60 1.08 0.73
67%
3 Land Development 53 0.10 0.10
95%
4 Construction of Well 44 0.66 0.59
90%
5 Construction of Road and Culvert 30 1.95 1.13
58%
6 Construction of Trench 27 2.31 1.95
84%
7 Constr of Cement Concrete Roads 26 0.43 0.51
118%
8 Plantation 16 0.37 0.06
16%
9 Construction of NADEP/Vermi Compost Pit 10 0.01 0.01
88%
10 Farm Pond 10 0.21 0.16
77%
11 Constr of Food Grain storage 9 0.00 0.04
0%
12 Well Recharge 8 0.09 0.05
62%
13 Terracing 8 0.09 0.06
69%
14 Solid and Liquid Waste Management 7 0.02 0.01
50%
15 Culvert 7 0.03 0.18
612%
16 Construction of Bund 5 0.05 0.01
22%
17 Construction of Percolation Tank 4 0.10 0.07
64%
18 Construction of Recharge Pits 3 0.00 0.00
42%
19 Constr of Aganwadi 3 0.19 0.17
92%
20 Repair & Maint of Community infrastructure 2 0.00 0.00
96%
21 Construction of Spur 1 0.01 0.00
9%
22 Community Sanitary Complex 1 0.00 0.00
86%
23 Constr of Compound wall 1 0.01 0.00
56%
24 Construction of Other Community Building/Assets 1 0.07 0.07
91%
25 Construction of Play field 1 0.02 0.00
24%
26 Boulder Check/Gully Plug 1 0.05 0.05
109%
27 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.02 0.02
98%
Total 769 8.71 6.81
All 27 rows (zero-value rows hidden) ⇩ Export to Excel