Works completed
204
Sanctioned (pure scheme)
₹1.74 Cr
Expenditure since inception
₹1.25 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
16 works
₹37.21 L sanctioned
₹14.28 L spent (38%)
02
Rural Housing
142 works
₹30.32 L sanctioned
₹29.38 L spent (97%)
03
Works for Flood Control and Protection
2 works
₹24.77 L sanctioned
₹23.26 L spent (94%)
04
Construction of Bund
4 works
₹18.14 L sanctioned
₹11.77 L spent (65%)
05
Plantation
5 works
₹11.26 L sanctioned
₹2.85 L spent (25%)
06
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹8.54 L sanctioned
₹6.55 L spent (77%)
07
Construction of Road and Culvert
2 works
₹7.75 L sanctioned
₹6.54 L spent (84%)
08
Construction of Percolation Tank
1 works
₹7.20 L sanctioned
₹6.78 L spent (94%)
09
Construction of Crematorium
4 works
₹7.20 L sanctioned
₹6.59 L spent (91%)
10
Land Development
3 works
₹5.37 L sanctioned
₹5.21 L spent (97%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 142 30.32 29.38
97%
2 Constr of Cement Concrete Roads 16 37.21 14.28
38%
3 Solid and Liquid Waste Management 10 0.54 0.48
90%
4 Plantation 5 11.26 2.85
25%
5 Construction of Crematorium 4 7.20 6.59
92%
6 Construction of Bund 4 18.14 11.77
65%
7 Land Development 3 5.37 5.21
97%
8 Construction of NADEP/Vermi Compost Pit 3 1.25 1.19
96%
9 Construction of Recharge Pits 3 0.43 0.42
97%
10 Construction of Road and Culvert 2 7.75 6.54
84%
11 Works for Flood Control and Protection 2 24.77 23.26
94%
12 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 8.54 6.55
77%
13 Constr of Aganwadi 1 3.12 1.76
56%
14 Construction of Percolation Tank 1 7.20 6.78
94%
15 Construction of Play field 1 4.32 2.59
60%
16 Community Sanitary Complex 1 0.47 0.46
97%
17 Construction of Well 1 2.55 2.55
100%
18 Farm Pond 1 0.56 0.51
92%
19 Repair & maint of Pond/ Tank 1 1.59 0.98
62%
20 Terracing 1 0.76 0.78
102%
21 Well Recharge 1 0.26 0.23
89%
Total 204 173.61 125.17