MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
464
Sanctioned (pure scheme)
₹3.89 Cr
Expenditure since inception
₹2.89 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
8 works
₹80.17 L sanctioned
₹52.88 L spent (66%)
02
Works for Flood Control and Protection
14 works
₹78.98 L sanctioned
₹72.77 L spent (92%)
03
Construction of Well
20 works
₹55.68 L sanctioned
₹44.57 L spent (80%)
04
Constr of Cement Concrete Roads
46 works
₹46.38 L sanctioned
₹26.20 L spent (57%)
05
Plantation
14 works
₹26.40 L sanctioned
₹6.25 L spent (24%)
06
Rural Housing
139 works
₹22.06 L sanctioned
₹21.92 L spent (99%)
07
Construction of Percolation Tank
5 works
₹21.56 L sanctioned
₹17.82 L spent (83%)
08
Farm Pond
98 works
₹16.72 L sanctioned
₹10.85 L spent (65%)
09
Construction of Tank
1 works
₹9.24 L sanctioned
₹8.20 L spent (89%)
10
Construction of Crematorium
4 works
₹7.20 L sanctioned
₹6.81 L spent (95%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 139 22.06 21.92
99%
2 Farm Pond 98 16.72 10.85
65%
3 Construction of Toilets 92 4.83 4.77
99%
4 Constr of Cement Concrete Roads 46 46.38 26.20
57%
5 Construction of Well 20 55.68 44.57
80%
6 Works for Flood Control and Protection 14 78.98 72.77
92%
7 Plantation 14 26.40 6.25
24%
8 Construction of Road and Culvert 8 80.17 52.88
66%
9 Solid and Liquid Waste Management 7 0.38 0.37
97%
10 Construction of NADEP/Vermi Compost Pit 5 2.39 2.13
89%
11 Construction of Percolation Tank 5 21.56 17.82
83%
12 Construction of Crematorium 4 7.20 6.81
95%
13 Well Recharge 3 0.78 0.76
98%
14 Construction of Check Dam/Stop Dam 1 3.10 1.41
46%
15 Construction of Bund 1 4.13 3.60
87%
16 Repair & maint of Pond/ Tank 1 2.54 2.48
98%
17 Constr of Kitchen Shed 1 0.16 0.15
96%
18 Constr of Aganwadi 1 1.80 1.59
88%
19 Construction of Play field 1 3.53 3.37
96%
20 Construction of Recharge Pits 1 0.36 0.10
29%
21 Community Sanitary Complex 1 0.44 0.43
99%
22 Construction of Tank 1 9.24 8.20
89%
Total 464 388.81 289.43
All 22 rows (zero-value rows hidden) ⇩ Export to Excel