Showcase — Completed Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
to
Reset filters
Scope
Works completed
333
Sanctioned (pure scheme)
₹3.87 Cr
Expenditure since inception
₹2.75 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
26 works
₹78.04 L sanctioned
₹72.16 L spent (92%)
02
Construction of Road and Culvert
4 works
₹46.60 L sanctioned
₹24.04 L spent (52%)
03
Rural Housing
233 works
₹41.10 L sanctioned
₹40.21 L spent (98%)
04
Works for Flood Control and Protection
4 works
₹36.38 L sanctioned
₹28.98 L spent (80%)
05
Construction of Check Dam/Stop Dam
6 works
₹33.10 L sanctioned
₹16.98 L spent (51%)
06
Construction of Bund
2 works
₹26.56 L sanctioned
₹17.97 L spent (68%)
07
Farm Pond
9 works
₹26.09 L sanctioned
₹19.84 L spent (76%)
08
Plantation
11 works
₹20.44 L sanctioned
₹4.95 L spent (24%)
09
Constr of Cement Concrete Roads
12 works
₹19.84 L sanctioned
₹7.72 L spent (39%)
10
Construction of Percolation Tank
7 works
₹15.09 L sanctioned
₹9.32 L spent (62%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 233 41.10 40.21
98%
2 Construction of Well 26 78.04 72.16
93%
3 Constr of Cement Concrete Roads 12 19.84 7.72
39%
4 Plantation 11 20.44 4.95
24%
5 Farm Pond 9 26.09 19.84
76%
6 Construction of Percolation Tank 7 15.09 9.32
62%
7 Construction of Check Dam/Stop Dam 6 33.10 16.98
51%
8 Construction of NADEP/Vermi Compost Pit 4 0.48 0.48
100%
9 Land Development 4 13.35 7.87
59%
10 Works for Flood Control and Protection 4 36.38 28.98
80%
11 Construction of Road and Culvert 4 46.60 24.04
52%
12 Construction of Trench 3 10.98 9.43
86%
13 Construction of Crematorium 2 3.76 3.31
88%
14 Construction of Bund 2 26.56 17.97
68%
15 Construction of Play field 1 3.53 0.33
9%
16 Constr of Aganwadi 1 5.00 4.93
99%
17 Community Sanitary Complex 1 0.44 0.43
98%
18 Repair & maint of Pond/ Tank 1 2.94 2.89
98%
19 Well Recharge 1 3.72 3.35
90%
20 Construction of Toilets 1 0.03 0.03
100%
Total 333 387.45 275.21