MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-08-10 08:33:03.460722
to
to
Reset filters
Scope
Works completed
263
Sanctioned (pure scheme)
₹3.80 Cr
Expenditure since inception
₹3.11 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Works for Flood Control and Protection
7 works
₹72.27 L sanctioned
₹63.33 L spent (88%)
02
Construction of Road and Culvert
4 works
₹65.17 L sanctioned
₹39.49 L spent (61%)
03
Construction of Percolation Tank
9 works
₹39.39 L sanctioned
₹35.53 L spent (90%)
04
Rural Housing
158 works
₹29.92 L sanctioned
₹29.55 L spent (99%)
05
Plantation
18 works
₹29.48 L sanctioned
₹12.76 L spent (43%)
06
Construction of Well
8 works
₹27.53 L sanctioned
₹26.41 L spent (96%)
07
Construction of Tank
3 works
₹22.33 L sanctioned
₹21.36 L spent (96%)
08
Repair & maint of Pond/ Tank
3 works
₹19.60 L sanctioned
₹16.15 L spent (82%)
09
Farm Pond
5 works
₹17.30 L sanctioned
₹16.24 L spent (94%)
10
Constr of Cement Concrete Roads
19 works
₹13.06 L sanctioned
₹12.33 L spent (94%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 158 29.92 29.55
99%
2 Constr of Cement Concrete Roads 19 13.06 12.33
94%
3 Plantation 18 29.48 12.76
43%
4 Construction of Percolation Tank 9 39.39 35.53
90%
5 Construction of Well 8 27.53 26.41
96%
6 Works for Flood Control and Protection 7 72.27 63.33
88%
7 Solid and Liquid Waste Management 6 0.32 0.30
94%
8 Farm Pond 5 17.30 16.24
94%
9 Construction of Road and Culvert 4 65.17 39.49
61%
10 Well Recharge 4 1.04 1.01
98%
11 Construction of NADEP/Vermi Compost Pit 3 0.24 0.22
92%
12 Repair & maint of Pond/ Tank 3 19.60 16.15
82%
13 Construction of Tank 3 22.33 21.36
96%
14 Constr of Aganwadi 3 6.72 3.89
58%
15 Construction of Crematorium 3 5.40 5.16
96%
16 Construction of Play field 2 7.06 6.03
85%
17 Construction of Check Dam/Stop Dam 2 1.82 1.79
98%
18 Repair & Maint of Check Dam/Stop Dam 2 1.80 1.34
74%
19 Construction of Trench 2 12.54 11.64
93%
20 Community Sanitary Complex 1 0.44 0.43
98%
21 Renovation of traditional water bodies 1 6.15 6.07
99%
Total 263 379.58 311.03
All 21 rows (zero-value rows hidden) ⇩ Export to Excel