MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
368
Sanctioned (pure scheme)
₹4.21 Cr
Expenditure since inception
₹2.45 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
33 works
₹1.98 Cr sanctioned
₹92.16 L spent (47%)
02
Construction of Road and Culvert
7 works
₹47.65 L sanctioned
₹21.72 L spent (46%)
03
Constr of Cement Concrete Roads
24 works
₹35.76 L sanctioned
₹31.23 L spent (87%)
04
Construction of Bund
66 works
₹35.33 L sanctioned
₹22.27 L spent (63%)
05
Rural Housing
146 works
₹28.09 L sanctioned
₹27.34 L spent (97%)
06
Plantation
6 works
₹14.21 L sanctioned
₹1.91 L spent (13%)
07
Construction of Trench
5 works
₹13.12 L sanctioned
₹7.99 L spent (61%)
08
Construction of Well
10 works
₹12.52 L sanctioned
₹8.08 L spent (65%)
09
Land Development
28 works
₹9.18 L sanctioned
₹6.49 L spent (71%)
10
Cattle Shed
8 works
₹6.24 L sanctioned
₹5.92 L spent (95%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 146 0.28 0.27
97%
2 Construction of Bund 66 0.35 0.22
63%
3 Construction of Check Dam/Stop Dam 33 1.98 0.92
47%
4 Land Development 28 0.09 0.06
71%
5 Constr of Cement Concrete Roads 24 0.36 0.31
87%
6 Construction of Well 10 0.13 0.08
65%
7 Farm Pond 10 0.03 0.03
84%
8 Cattle Shed 8 0.06 0.06
95%
9 Construction of Road and Culvert 7 0.48 0.22
46%
10 Plantation 6 0.14 0.02
14%
11 Construction of Toilets 5 0.01 0.01
100%
12 Construction of Trench 5 0.13 0.08
61%
13 Poultry Shelter 5 0.03 0.02
88%
14 Goat Shelter 4 0.02 0.02
90%
15 Works for Flood Control and Protection 3 0.01 0.01
91%
16 Construction of Tank 2 0.00 0.00
95%
17 Community Sanitary Complex 2 0.01 0.01
92%
18 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.01 0.01
99%
19 Renovation of traditional water bodies 1 0.05 0.05
106%
20 Construction of Crematorium 1 0.02 0.02
91%
21 Construction of Play field 1 0.04 0.03
81%
Total 368 4.21 2.45
All 21 rows (zero-value rows hidden) ⇩ Export to Excel