Scope
Works completed
369
Sanctioned (pure scheme)
₹2.23 Cr
Expenditure since inception
₹1.44 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
270 works
₹43.48 L sanctioned
₹42.39 L spent (97%)
02
Plantation
9 works
₹29.80 L sanctioned
₹2.65 L spent (9%)
03
Renovation of traditional water bodies
4 works
₹19.19 L sanctioned
₹7.46 L spent (39%)
04
Land Development
6 works
₹18.61 L sanctioned
₹12.24 L spent (66%)
05
Construction of Tank
2 works
₹18.59 L sanctioned
₹17.22 L spent (93%)
06
Constr of Cement Concrete Roads
14 works
₹15.04 L sanctioned
₹10.77 L spent (72%)
07
Repair & maint of Pond/ Tank
2 works
₹13.28 L sanctioned
₹9.15 L spent (69%)
08
Construction of Bund
27 works
₹12.80 L sanctioned
₹4.42 L spent (35%)
09
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹11.20 L sanctioned
₹7.15 L spent (64%)
10
Construction of Trench
1 works
₹7.99 L sanctioned
₹6.30 L spent (79%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 270 43.48 42.39
98%
2 Construction of Bund 27 12.80 4.42
35%
3 Constr of Cement Concrete Roads 14 15.04 10.77
72%
4 Plantation 9 29.80 2.65
9%
5 Construction of NADEP/Vermi Compost Pit 8 1.45 1.17
80%
6 Cattle Shed 7 6.65 0.10
2%
7 Land Development 6 18.61 12.24
66%
8 Renovation of traditional water bodies 4 19.19 7.46
39%
9 Repair & maint of Water Harvesting Structures 4 0.77 0.18
23%
10 Construction of Road and Culvert 4 6.11 7.85
128%
11 Solid and Liquid Waste Management 4 0.05 0.05
100%
12 Construction of Tank 2 18.59 17.22
93%
13 Constr of Aganwadi 2 5.71 4.66
82%
14 Repair & maint of Pond/ Tank 2 13.28 9.15
69%
15 Repair & Maint of Check Dam/Stop Dam 1 5.64 5.60
99%
16 Construction of Play field 1 3.53 2.39
68%
17 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 11.20 7.15
64%
18 Construction of Crematorium 1 2.01 2.00
100%
19 Construction of Trench 1 7.99 6.30
79%
20 Boulder Check/Gully Plug 1 0.97 0.64
65%
Total 369 222.88 144.38
All 20 rows (zero-value rows hidden) ⇩ Export to Excel