MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
798
Sanctioned (pure scheme)
₹10.50 Cr
Expenditure since inception
₹7.98 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
118 works
₹2.01 Cr sanctioned
₹1.79 Cr spent (89%)
02
Construction of Trench
38 works
₹1.79 Cr sanctioned
₹1.40 Cr spent (78%)
03
Construction of Road and Culvert
21 works
₹1.08 Cr sanctioned
₹78.28 L spent (73%)
04
Construction of Bund
124 works
₹98.50 L sanctioned
₹82.87 L spent (84%)
05
Plantation
16 works
₹90.42 L sanctioned
₹27.16 L spent (30%)
06
Boulder Check/Gully Plug
32 works
₹77.28 L sanctioned
₹63.69 L spent (82%)
07
Farm Pond
85 works
₹54.41 L sanctioned
₹41.31 L spent (76%)
08
Rural Housing
275 works
₹49.27 L sanctioned
₹47.40 L spent (96%)
09
Construction of Tank
1 works
₹39.92 L sanctioned
₹35.21 L spent (88%)
10
Land Development
29 works
₹28.96 L sanctioned
₹19.47 L spent (67%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 275 0.49 0.47
96%
2 Construction of Bund 124 0.99 0.83
84%
3 Construction of Check Dam/Stop Dam 118 2.01 1.79
89%
4 Farm Pond 85 0.54 0.41
76%
5 Construction of Trench 38 1.79 1.40
78%
6 Boulder Check/Gully Plug 32 0.77 0.64
82%
7 Land Development 29 0.29 0.19
67%
8 Construction of Road and Culvert 21 1.08 0.78
73%
9 Constr of Cement Concrete Roads 17 0.25 0.19
78%
10 Plantation 16 0.90 0.27
30%
11 Construction of NADEP/Vermi Compost Pit 8 0.02 0.01
77%
12 Well Recharge 6 0.02 0.01
64%
13 Repair & maint of Water Harvesting Structures 5 0.12 0.09
81%
14 Construction of Well 4 0.09 0.05
53%
15 Construction of Recharge Pits 3 0.00 0.00
67%
16 Construction of Other Community Building/Assets 2 0.00 0.00
41%
17 Constr of Gabion 2 0.17 0.04
22%
18 Terracing 2 0.17 0.14
85%
19 Poultry Shelter 2 0.01 0.01
90%
20 Community Sanitary Complex 1 0.00 0.00
100%
21 Construction of Play field 1 0.02 0.00
3%
22 Construction of Tank 1 0.40 0.35
88%
23 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.00 0.00
81%
24 Culvert 1 0.23 0.23
99%
25 Other Works 1 0.01 0.00
70%
26 Renovation of traditional water bodies 1 0.02 0.02
70%
27 Repair & Maint of Check Dam/Stop Dam 1 0.03 0.03
98%
28 Repair & maint of Road 1 0.08 0.00
4%
Total 798 10.50 7.98
All 28 rows (zero-value rows hidden) ⇩ Export to Excel