MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
556
Sanctioned (pure scheme)
₹11.82 Cr
Expenditure since inception
₹6.26 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
72 works
₹5.21 Cr sanctioned
₹1.00 Cr spent (19%)
02
Boulder Check/Gully Plug
33 works
₹2.51 Cr sanctioned
₹2.13 Cr spent (85%)
03
Construction of Bund
70 works
₹1.07 Cr sanctioned
₹71.91 L spent (67%)
04
Farm Pond
59 works
₹51.00 L sanctioned
₹36.79 L spent (72%)
05
Rural Housing
222 works
₹49.70 L sanctioned
₹46.97 L spent (95%)
06
Plantation
18 works
₹48.58 L sanctioned
₹26.25 L spent (54%)
07
Repair & maint of Pond/ Tank
5 works
₹40.50 L sanctioned
₹30.94 L spent (76%)
08
Construction of Road and Culvert
14 works
₹37.86 L sanctioned
₹41.15 L spent (109%)
09
Construction of Tank
6 works
₹36.21 L sanctioned
₹30.00 L spent (83%)
10
Constr of Cement Concrete Roads
6 works
₹13.79 L sanctioned
₹4.40 L spent (32%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 222 0.50 0.47
95%
2 Construction of Check Dam/Stop Dam 72 5.21 1.00
19%
3 Construction of Bund 70 1.07 0.72
67%
4 Farm Pond 59 0.51 0.37
72%
5 Boulder Check/Gully Plug 33 2.51 2.13
85%
6 Construction of NADEP/Vermi Compost Pit 22 0.06 0.05
87%
7 Plantation 18 0.49 0.26
54%
8 Construction of Road and Culvert 14 0.38 0.41
109%
9 Land Development 10 0.02 0.04
228%
10 Construction of Tank 6 0.36 0.30
83%
11 Constr of Cement Concrete Roads 6 0.14 0.04
32%
12 Repair & maint of Pond/ Tank 5 0.41 0.31
76%
13 Well Recharge 3 0.05 0.07
125%
14 Construction of Trench 3 0.01 0.01
105%
15 Construction of Crematorium 2 0.04 0.03
96%
16 Construction of Percolation Tank 2 0.03 0.00
14%
17 Construction of Recharge Pits 2 0.01 0.00
44%
18 Constr of Aganwadi 2 0.00 0.00
86%
19 Roof Water Harvesting on gov/panchayat bldg 2 0.00 0.00
92%
20 Construction of Well 1 0.02 0.01
40%
21 Community Sanitary Complex 1 0.00 0.00
97%
22 Constr of Gabion 1 0.01 0.01
85%
Total 556 11.82 6.26
All 22 rows (zero-value rows hidden) ⇩ Export to Excel