MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
403
Sanctioned (pure scheme)
₹7.72 Cr
Expenditure since inception
₹5.96 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
24 works
₹1.68 Cr sanctioned
₹1.44 Cr spent (86%)
02
Farm Pond
51 works
₹1.68 Cr sanctioned
₹1.33 Cr spent (79%)
03
Construction of Tank
19 works
₹85.67 L sanctioned
₹57.57 L spent (67%)
04
Construction of Road and Culvert
10 works
₹78.78 L sanctioned
₹52.80 L spent (67%)
05
Construction of Check Dam/Stop Dam
17 works
₹78.40 L sanctioned
₹59.65 L spent (76%)
06
Construction of Recharge Pits
14 works
₹46.83 L sanctioned
₹36.40 L spent (78%)
07
Rural Housing
161 works
₹31.43 L sanctioned
₹29.46 L spent (94%)
08
Land Development
42 works
₹21.78 L sanctioned
₹15.06 L spent (69%)
09
Underground Dyke for Ground Water Recharge
2 works
₹14.78 L sanctioned
₹11.48 L spent (78%)
10
Construction of Bund
1 works
₹14.59 L sanctioned
₹12.47 L spent (85%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 161 0.31 0.29
94%
2 Farm Pond 51 1.68 1.33
79%
3 Land Development 42 0.22 0.15
69%
4 Construction of Trench 24 1.68 1.44
86%
5 Construction of NADEP/Vermi Compost Pit 24 0.01 0.01
73%
6 Construction of Tank 19 0.86 0.58
67%
7 Construction of Check Dam/Stop Dam 17 0.78 0.60
76%
8 Construction of Recharge Pits 14 0.47 0.36
78%
9 Constr of Cement Concrete Roads 11 0.13 0.11
80%
10 Construction of Road and Culvert 10 0.79 0.53
67%
11 Construction of Toilets 6 0.01 0.01
100%
12 Construction of Well 4 0.03 0.03
94%
13 Construction of Crematorium 4 0.12 0.10
82%
14 Underground Dyke for Ground Water Recharge 2 0.15 0.11
78%
15 Plantation 2 0.07 0.00
1%
16 Solid and Liquid Waste Management 2 0.02 0.02
95%
17 Constr of Gabion 2 0.07 0.05
72%
18 Well Recharge 1 0.02 0.02
85%
19 Community Sanitary Complex 1 0.01 0.00
51%
20 Constr of GP Bhawan 1 0.00 0.00
90%
21 Construction of Bund 1 0.15 0.12
85%
22 Construction of Canal 1 0.05 0.03
58%
23 Construction of Percolation Tank 1 0.03 0.03
74%
24 Construction of Play field 1 0.02 0.00
9%
25 Terracing 1 0.05 0.04
78%
Total 403 7.72 5.96
All 25 rows (zero-value rows hidden) ⇩ Export to Excel