Completion Progress

Reset location
Completed in 2026-2027
2,262
— started this same FY
633
28%
— started in an earlier FY
1,629
72% — carried over
Physically done, closure pending
2,262
This period's completions, by original start year
2025-2026
1,187
2026-2027
633
2024-2025
359
2023-2024
24
2022-2023
18
2021-2022
13
Completions by month, FY 2026-2027
Jun
Jul
Aug
Sep

Detailed breakdown

By Block By New Work Type
Sr. Block Completed this period — started same FY — carried over
1 REHLI 617 334 283
2 BINA 387 96 291
3 SAGAR 304 67 237
4 DEORI 205 47 158
5 SHAHGARH 159 4 155
6 MALTHONE 155 7 148
7 KESLI 127 12 115
8 BANDA 117 20 97
9 KHURAI 66 17 49
10 RAHATGARH 65 8 57
11 JAISINAGAR 60 21 39
Total 2,262 633 1,629
All 11 rows (zero-value rows hidden) ⇩ Export to Excel