MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Completion Progress

Reset location
Completed in 2026-2027
1,275
— started this same FY
197
15%
— started in an earlier FY
1,078
85% — carried over
Physically done, closure pending
1,275
This period's completions, by original start year
2025-2026
928
2026-2027
197
2024-2025
124
2023-2024
17
2022-2023
6
2020-2021
2
Completions by month, FY 2026-2027
Jun
Jul
Aug

Detailed breakdown

By Block By New Work Type
Sr. Block Completed this period — started same FY — carried over
1 SITAMAU 438 59 379
2 MANDSAUR 363 63 300
3 MALHARGARH 171 23 148
4 GAROTH 169 41 128
5 BHANPURA 134 11 123
Total 1,275 197 1,078
All 5 rows (zero-value rows hidden) ⇩ Export to Excel