| Sr. | New Work Type | Completed this period | — started same FY | — carried over |
|---|---|---|---|---|
| 1 | Rural Housing | 728 | 35 | 693 |
| 2 | Well Recharge | 194 | 0 | 194 |
| 3 | Farm Pond | 168 | 0 | 168 |
| 4 | Construction of Check Dam/Stop Dam | 49 | 0 | 49 |
| 5 | Plantation | 48 | 0 | 48 |
| 6 | Works for Flood Control and Protection | 29 | 0 | 29 |
| 7 | Land Development | 16 | 0 | 16 |
| 8 | Repair & maint of Pond/ Tank | 16 | 0 | 16 |
| 9 | Construction of Tank | 16 | 0 | 16 |
| 10 | Construction of Recharge Pits | 12 | 0 | 12 |
| 11 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 11 | 0 | 11 |
| 12 | Construction of Bund | 11 | 0 | 11 |
| 13 | Construction of Well | 8 | 0 | 8 |
| 14 | Construction of Trench | 6 | 0 | 6 |
| 15 | Lining of Canal | 3 | 0 | 3 |
| 16 | Construction of Canal | 3 | 0 | 3 |
| 17 | Grass Land Development | 3 | 0 | 3 |
| 18 | Constr of Cement Concrete Roads | 3 | 0 | 3 |
| 19 | Renovation of Canal | 3 | 0 | 3 |
| 20 | Repair & maint of Water Harvesting Structures | 3 | 0 | 3 |
| 21 | Underground Dyke for Ground Water Recharge | 2 | 0 | 2 |
| 22 | Construction of Percolation Tank | 2 | 0 | 2 |
| 23 | Repair & Maint of Check Dam/Stop Dam | 2 | 0 | 2 |
| 24 | Nursery Development | 1 | 0 | 1 |
| 25 | Repaire and Maint of NADEP/Vermi Compost Pit | 1 | 0 | 1 |
| 26 | Solid and Liquid Waste Management | 1 | 0 | 1 |
| 27 | Repair & maint of Road | 1 | 0 | 1 |
| 28 | Constr of Gabion | 1 | 0 | 1 |
| Total | 1,341 | 35 | 1,306 |