Completion Progress

Reset location
Completed in 2026-2027
1,913
— started this same FY
518
27%
— started in an earlier FY
1,395
73% — carried over
Physically done, closure pending
1,608
This period's completions, by original start year
2025-2026
876
2026-2027
518
2024-2025
241
2023-2024
109
2021-2022
71
2022-2023
55
Completions by month, FY 2026-2027
Mar
Apr
May
Jun
Jul
Aug
Sep

Detailed breakdown

By Panchayat By New Work Type
Sr. Panchayat Completed this period — started same FY — carried over
1 Chamarumariya 87 0 87
2 Shaharkheda 73 46 27
3 Veerpurkala 66 42 24
4 Bhatoli 65 0 65
5 Okhlikheda 63 48 15
6 Deharipama 57 14 43
7 Nassobarri 55 50 5
8 Murarira 55 46 9
9 Patherachandu 54 15 39
10 Ishrwas 49 0 49
11 Malniya 48 14 34
12 GolaKheda 46 29 17
13 Tonkara 45 5 40
14 Mahoti 44 33 11
15 Jamuniyakala 42 6 36
16 Sawankhedi 42 20 22
17 Anandapur 41 0 41
18 Tajpura 40 11 29
19 Wapcha 38 3 35
20 Mahaban 37 19 18
21 Chandbad 36 1 35
22 Tiloini 34 0 34
23 Motipur 34 0 34
24 Balrampur 34 26 8
25 Nainwas Kala 33 0 33
26 Gopalpur 33 8 25
27 Masoodi 31 16 15
28 Jarsena 30 5 25
29 Semri Ahir 30 0 30
30 Jabti 29 1 28
31 Chhirari 27 0 27
32 Murwas 27 0 27
33 Dondkheda 25 8 17
34 Sunkher 24 11 13
35 kherkhedikhurd 23 2 21
36 Agarapathar 23 1 22
37 Barkheda Ghosi 22 0 22
38 Narayanpurkala 22 2 20
39 Parwariya 21 2 19
40 Mundararatansi 20 2 18
41 Mundala 20 3 17
42 Jhukarjogi 20 4 16
43 Kaladev 20 0 20
44 Dhiragarah 19 0 19
45 Titarbarri 18 0 18
46 Bamankhedi 17 3 14
47 Mdawta 17 2 15
48 Dharga 17 0 17
49 Beeju Khedi 17 1 16
50 Semrameghanath 16 2 14
51 Danwas 16 1 15
52 Muskra 15 0 15
53 Bairagarah 14 0 14
54 Rusiya 12 6 6
55 Unarsikala 12 0 12
56 Vanarasi 12 0 12
57 Koluapathar 11 0 11
58 Kachhikheda 10 0 10
59 Rusallisahu 9 0 9
60 Lalchiya 8 4 4
61 Moondarasagar 8 6 2
Total 1,913 518 1,395
All 61 rows (zero-value rows hidden) ⇩ Export to Excel