Completion Progress

Reset location
Completed in 2026-2027
3,429
— started this same FY
1,411
41%
— started in an earlier FY
2,018
59% — carried over
Physically done, closure pending
2,978
This period's completions, by original start year
2025-2026
1,607
2026-2027
1,411
2024-2025
286
2022-2023
59
2023-2024
29
2021-2022
15
Completions by month, FY 2026-2027
Jun
Jul
Aug

Detailed breakdown

By Block By New Work Type
Sr. Block Completed this period — started same FY — carried over
1 RAGHOGARH 1,164 815 349
2 BAMORI 921 279 642
3 GUNA 649 176 473
4 ARON 394 102 292
5 CHANCHODA 301 39 262
Total 3,429 1,411 2,018
All 5 rows (zero-value rows hidden) ⇩ Export to Excel