Completed in 2026-2027
2,106
— started this same FY
289
14%
— started in an earlier FY
1,817
86% — carried over
Physically done, closure pending
1,578
This period's completions, by original start year
2025-2026
1,253
2024-2025
476
2026-2027
289
2023-2024
46
2022-2023
24
2021-2022
7
Completions by month, FY 2026-2027
Jun
Jul

Detailed breakdown

By Block By New Work Type
Sr. Block Completed this period — started same FY — carried over
1 MAHESHWAR 514 18 496
2 BARWAH 421 76 345
3 KASRAWAD 409 91 318
4 ZIRANYA 264 15 249
5 BHAGVANPURA 178 0 178
6 BHIKANGAON 139 38 101
7 GOGANWA 82 48 34
8 SEGAON 79 1 78
9 KHARGONE 20 2 18
Total 2,106 289 1,817