Completion Progress

Reset location
Completed in 2026-2027
6,686
— started this same FY
130
2%
— started in an earlier FY
6,556
98% — carried over
Physically done, closure pending
7,069
This period's completions, by original start year
2025-2026
5,444
2024-2025
590
2023-2024
299
2026-2027
130
2020-2021
74
2021-2022
66
Completions by month, FY 2026-2027
Mar
Apr
May
Jun
Jul
Aug

Detailed breakdown

By Block By New Work Type
Sr. Block Completed this period — started same FY — carried over
1 ASHTA 2,252 81 2,171
2 SEHORE 1,503 19 1,484
3 NASRULLAGANJ 1,251 17 1,234
4 ICHHAWAR 882 11 871
5 BUDNI 798 2 796
Total 6,686 130 6,556