MGNREGA Works Dashboard
Admin login

Completion Progress

Reset location
Completed in 2026-2027
10,084
— started this same FY
867
9%
— started in an earlier FY
9,217
91% — carried over
Physically done, closure pending
9,584
This period's completions, by original start year
2025-2026
5,221
2024-2025
2,218
2023-2024
1,150
2026-2027
867
2022-2023
300
2021-2022
210
Completions by month, FY 2026-2027
Mar
Apr
May
Jun
Jul

Detailed breakdown

By Block By New Work Type
Sr. Block Completed this period — started same FY — carried over
1 BAIHAR 1,506 10 1,496
2 BIRSA 1,301 9 1,292
3 KATANGI 1,185 240 945
4 KIRNAPUR 1,078 181 897
5 PARASWADA 971 47 924
6 LALBARRA 939 91 848
7 WARASEONI 837 172 665
8 KHAIRLANJI 830 35 795
9 BALAGHAT 765 34 731
10 LANJI 672 48 624
Total 10,084 867 9,217
All 10 rows (zero-value rows hidden) ⇩ Export to Excel