| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 101 | 15 | 86 | 0 | 19.98 | 18.01 | 90% |
| 2 | Constr of Cement Concrete Roads | 58 | 0 | 48 | 9 | 19.67 | 17.07 | 87% |
| 3 | Construction of Recharge Pits | 14 | 0 | 7 | 5 | 1.83 | 0.99 | 54% |
| 4 | Construction of Road and Culvert | 11 | 0 | 3 | 3 | 55.32 | 25.11 | 45% |
| 5 | Construction of Trench | 10 | 0 | 6 | 3 | 11.46 | 8.66 | 76% |
| 6 | Well Recharge | 9 | 0 | 8 | 1 | 10.57 | 9.61 | 91% |
| 7 | Plantation | 8 | 2 | 4 | 2 | 22.59 | 4.79 | 21% |
| 8 | Construction of Well | 7 | 0 | 5 | 0 | 11.74 | 4.89 | 42% |
| 9 | Cattle Shed | 4 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 10 | Construction of NADEP/Vermi Compost Pit | 4 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 11 | Farm Pond | 4 | 0 | 1 | 0 | 1.48 | 1.12 | 76% |
| 12 | Construction of Tank | 3 | 0 | 1 | 1 | 6.41 | 1.44 | 22% |
| 13 | Construction of Crematorium | 2 | 0 | 2 | 0 | 6.98 | 3.31 | 47% |
| 14 | Repair & maint of Pond/ Tank | 2 | 0 | 2 | 0 | 3.72 | 2.45 | 66% |
| 15 | Constr of Aganwadi | 2 | 0 | 2 | 0 | 3.90 | 3.38 | 87% |
| 16 | Solid and Liquid Waste Management | 2 | 0 | 0 | 1 | 0.19 | 0.00 | 0% |
| 17 | Construction of Toilets | 1 | 0 | 0 | 1 | 0.10 | 0.00 | 0% |
| 18 | Construction of Play field | 1 | 0 | 1 | 0 | 3.20 | 2.01 | 63% |
| 19 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.47 | 0.47 | 100% |
| 20 | Land Development | 1 | 0 | 0 | 1 | 1.48 | 0.00 | 0% |
| 21 | Repair & Maint of Community infrastructure | 1 | 0 | 1 | 0 | 5.18 | 0.46 | 9% |
| Total | 246 | 17 | 178 | 27 | 186.27 | 103.74 |