| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 93 | 37 | 34 | 0 | 19.83 | 13.34 | 67% |
| 2 | Construction of Well | 34 | 0 | 19 | 1 | 7.70 | 14.42 | 187% |
| 3 | Farm Pond | 23 | 0 | 17 | 1 | 28.68 | 26.26 | 92% |
| 4 | Construction of Road and Culvert | 22 | 0 | 16 | 0 | 81.97 | 60.15 | 73% |
| 5 | Construction of Toilets | 18 | 0 | 4 | 2 | 7.50 | 0.86 | 12% |
| 6 | Plantation | 15 | 1 | 11 | 1 | 47.07 | 13.85 | 29% |
| 7 | Well Recharge | 8 | 0 | 6 | 0 | 9.35 | 4.48 | 48% |
| 8 | Construction of Trench | 7 | 1 | 4 | 1 | 13.95 | 8.07 | 58% |
| 9 | Solid and Liquid Waste Management | 7 | 0 | 0 | 1 | 0.54 | 0.00 | 0% |
| 10 | Construction of Bund | 6 | 0 | 5 | 0 | 9.81 | 7.16 | 73% |
| 11 | Construction of Percolation Tank | 3 | 1 | 0 | 2 | 6.25 | 2.33 | 37% |
| 12 | Construction of Check Dam/Stop Dam | 3 | 0 | 2 | 0 | 7.81 | 4.07 | 52% |
| 13 | Underground Dyke for Ground Water Recharge | 3 | 0 | 1 | 0 | 4.81 | 2.84 | 59% |
| 14 | Constr of Cement Concrete Roads | 2 | 0 | 2 | 0 | 3.61 | 1.62 | 45% |
| 15 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0 | 0 | 2 | 7.10 | 0.00 | 0% |
| 16 | Roof Water Harvesting on gov/panchayat bldg | 2 | 0 | 0 | 2 | 0.38 | 0.00 | 0% |
| 17 | Boulder Check/Gully Plug | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 18 | Construction of Crematorium | 1 | 0 | 0 | 0 | 2.65 | 2.45 | 93% |
| 19 | Construction of Play field | 1 | 0 | 1 | 0 | 1.87 | 0.79 | 42% |
| 20 | Construction of Tank | 1 | 0 | 1 | 0 | 2.18 | 2.05 | 94% |
| 21 | Constr of Compound wall | 1 | 0 | 0 | 1 | 8.13 | 0.00 | 0% |
| 22 | Construction of Recharge Pits | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 23 | Constr of Gabion | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 24 | Land Development | 1 | 0 | 1 | 0 | 3.97 | 3.85 | 97% |
| Total | 257 | 40 | 124 | 17 | 275.17 | 168.61 |