| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 231 | 0 | 225 | 0 | 36.69 | 35.06 | 96% |
| 2 | Construction of Bund | 62 | 0 | 19 | 38 | 19.98 | 14.52 | 73% |
| 3 | Solid and Liquid Waste Management | 30 | 1 | 8 | 11 | 1.56 | 0.98 | 63% |
| 4 | Construction of NADEP/Vermi Compost Pit | 23 | 0 | 5 | 13 | 0.36 | 0.12 | 33% |
| 5 | Construction of Trench | 19 | 0 | 9 | 6 | 47.74 | 28.55 | 60% |
| 6 | Construction of Well | 18 | 0 | 13 | 0 | 19.68 | 10.30 | 52% |
| 7 | Plantation | 18 | 3 | 8 | 4 | 67.23 | 14.50 | 22% |
| 8 | Construction of Check Dam/Stop Dam | 17 | 0 | 9 | 4 | 26.11 | 29.69 | 114% |
| 9 | Boulder Check/Gully Plug | 15 | 0 | 0 | 6 | 0.00 | 0.00 | 0% |
| 10 | Land Development | 11 | 0 | 10 | 0 | 6.55 | 4.91 | 75% |
| 11 | Well Recharge | 8 | 0 | 4 | 0 | 1.91 | 0.09 | 5% |
| 12 | Constr of Cement Concrete Roads | 8 | 0 | 5 | 1 | 4.92 | 3.35 | 68% |
| 13 | Cattle Shed | 7 | 0 | 4 | 0 | 4.70 | 3.38 | 72% |
| 14 | Construction of Tank | 6 | 0 | 5 | 1 | 8.30 | 7.09 | 86% |
| 15 | Roof Water Harvesting on gov/panchayat bldg | 6 | 0 | 5 | 0 | 0.36 | 0.10 | 27% |
| 16 | Construction of Road and Culvert | 5 | 0 | 4 | 0 | 57.94 | 29.71 | 51% |
| 17 | Construction of Percolation Tank | 4 | 0 | 1 | 3 | 8.71 | 5.25 | 60% |
| 18 | Constr of Kitchen Shed | 4 | 0 | 3 | 0 | 0.81 | 0.56 | 69% |
| 19 | Farm Pond | 4 | 1 | 1 | 0 | 8.34 | 0.17 | 2% |
| 20 | Repair & maint of Pond/ Tank | 3 | 0 | 1 | 0 | 23.29 | 12.71 | 55% |
| 21 | Construction of Recharge Pits | 3 | 0 | 0 | 3 | 0.30 | 0.00 | 0% |
| 22 | Constr of Aganwadi | 2 | 0 | 1 | 0 | 1.80 | 1.63 | 91% |
| 23 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0 | 0 | 0 | 6.41 | 0.00 | 0% |
| 24 | Repair & maint of Water Harvesting Structures | 2 | 0 | 1 | 0 | 7.00 | 4.89 | 70% |
| 25 | Community Sanitary Complex | 2 | 0 | 1 | 0 | 0.50 | 0.50 | 100% |
| 26 | Terracing | 1 | 0 | 1 | 0 | 3.56 | 2.92 | 82% |
| 27 | Grass Land Development | 1 | 0 | 0 | 1 | 9.45 | 0.00 | 0% |
| 28 | Construction of Play field | 1 | 0 | 1 | 0 | 3.53 | 1.77 | 50% |
| 29 | Construction of Crematorium | 1 | 0 | 1 | 0 | 1.80 | 1.74 | 97% |
| 30 | Repair & Maint of Bund | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 31 | Repair & maint of Road | 1 | 0 | 1 | 0 | 0.87 | 0.88 | 101% |
| Total | 516 | 5 | 346 | 92 | 380.38 | 215.36 |