| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Constr of Cement Concrete Roads | 49 | 0 | 36 | 1 | 29.83 | 21.88 | 73% |
| 2 | Construction of Toilets | 21 | 0 | 12 | 0 | 1.83 | 1.31 | 72% |
| 3 | Rural Housing | 21 | 8 | 10 | 0 | 4.02 | 2.96 | 74% |
| 4 | Construction of Road and Culvert | 10 | 0 | 3 | 1 | 22.62 | 11.36 | 50% |
| 5 | Constr of Aganwadi | 10 | 0 | 4 | 1 | 15.29 | 9.71 | 64% |
| 6 | Land Development | 8 | 0 | 3 | 0 | 7.24 | 0.10 | 1% |
| 7 | Plantation | 6 | 0 | 4 | 1 | 17.31 | 1.72 | 10% |
| 8 | Construction of Crematorium | 4 | 0 | 3 | 0 | 6.17 | 6.00 | 97% |
| 9 | Construction of Play field | 3 | 0 | 1 | 0 | 1.87 | 0.04 | 2% |
| 10 | Construction of Bund | 3 | 0 | 0 | 3 | 10.98 | 0.00 | 0% |
| 11 | Well Recharge | 2 | 0 | 1 | 1 | 0.57 | 0.13 | 22% |
| 12 | Works for Flood Control and Protection | 1 | 0 | 1 | 0 | 2.82 | 2.41 | 85% |
| 13 | Community Sanitary Complex | 1 | 0 | 0 | 1 | 0.37 | 0.00 | 0% |
| 14 | Construction of Check Dam/Stop Dam | 1 | 0 | 0 | 1 | 2.03 | 0.00 | 0% |
| 15 | Construction of NADEP/Vermi Compost Pit | 1 | 0 | 1 | 0 | 0.05 | 0.03 | 55% |
| 16 | Culvert | 1 | 0 | 1 | 0 | 0.30 | 0.29 | 95% |
| 17 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 0.93 | 0.87 | 94% |
| 18 | Repair & Maint of Community infrastructure | 1 | 0 | 0 | 0 | 7.25 | 0.00 | 0% |
| 19 | Repair & maint of Pond/ Tank | 1 | 0 | 0 | 1 | 2.93 | 0.00 | 0% |
| 20 | Solid and Liquid Waste Management | 1 | 0 | 0 | 1 | 0.10 | 0.00 | 0% |
| 21 | Cattle Shed | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 147 | 8 | 81 | 12 | 134.50 | 58.81 |