| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 122 | 36 | 74 | 0 | 24.71 | 17.32 | 70% |
| 2 | Constr of Cement Concrete Roads | 88 | 0 | 54 | 9 | 40.44 | 27.11 | 67% |
| 3 | Construction of Toilets | 81 | 0 | 45 | 0 | 3.47 | 1.73 | 50% |
| 4 | Cattle Shed | 70 | 2 | 14 | 25 | 21.38 | 12.55 | 59% |
| 5 | Land Development | 61 | 0 | 25 | 1 | 17.23 | 4.04 | 24% |
| 6 | Plantation | 49 | 5 | 23 | 5 | 24.51 | 2.26 | 9% |
| 7 | Construction of Bund | 39 | 0 | 23 | 16 | 28.14 | 18.32 | 65% |
| 8 | Farm Pond | 28 | 0 | 21 | 4 | 67.66 | 36.79 | 54% |
| 9 | Construction of NADEP/Vermi Compost Pit | 24 | 1 | 17 | 6 | 1.34 | 0.36 | 27% |
| 10 | Works for Flood Control and Protection | 22 | 1 | 11 | 10 | 25.99 | 15.58 | 60% |
| 11 | Construction of Road and Culvert | 19 | 1 | 6 | 1 | 71.32 | 20.34 | 29% |
| 12 | Construction of Tank | 11 | 1 | 1 | 5 | 49.45 | 22.72 | 46% |
| 13 | Solid and Liquid Waste Management | 10 | 0 | 8 | 2 | 0.18 | 0.09 | 52% |
| 14 | Repair & maint of Pond/ Tank | 9 | 0 | 1 | 7 | 0.48 | 0.34 | 72% |
| 15 | Constr of GP Bhawan | 7 | 0 | 5 | 2 | 10.76 | 10.58 | 98% |
| 16 | Construction of Check Dam/Stop Dam | 7 | 0 | 2 | 3 | 5.67 | 3.63 | 64% |
| 17 | Constr of Compound wall | 3 | 1 | 2 | 0 | 4.60 | 2.50 | 54% |
| 18 | Constr of Aganwadi | 2 | 1 | 0 | 1 | 3.60 | 1.47 | 41% |
| 19 | Construction of Play field | 2 | 0 | 1 | 0 | 3.60 | 0.16 | 4% |
| 20 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 1 | 0 | 0 | 31.27 | 25.51 | 82% |
| 21 | Culvert | 2 | 0 | 2 | 0 | 1.20 | 1.08 | 90% |
| 22 | Construction of Canal | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 23 | Constr of Food Grain storage | 2 | 1 | 0 | 1 | 8.40 | 0.01 | 0% |
| 24 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 0.93 | 0.42 | 45% |
| 25 | Construction of Well | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 26 | Roof Water Harvesting on gov/panchayat bldg | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 27 | Construction of Trench | 1 | 0 | 0 | 0 | 12.14 | 9.60 | 79% |
| 28 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 9.00 | 4.83 | 54% |
| 29 | Construction of Crematorium | 1 | 0 | 0 | 1 | 0.49 | 0.00 | 0% |
| Total | 668 | 51 | 337 | 100 | 467.95 | 239.34 |