| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 305 | 31 | 263 | 1 | 55.10 | 51.76 | 94% |
| 2 | Construction of Check Dam/Stop Dam | 66 | 12 | 26 | 19 | 79.25 | 69.18 | 87% |
| 3 | Construction of Bund | 44 | 0 | 23 | 13 | 80.30 | 69.60 | 87% |
| 4 | Land Development | 37 | 0 | 27 | 5 | 33.78 | 12.55 | 37% |
| 5 | Construction of Toilets | 33 | 0 | 0 | 12 | 3.08 | 0.00 | 0% |
| 6 | Farm Pond | 32 | 5 | 10 | 0 | 35.68 | 28.25 | 79% |
| 7 | Plantation | 31 | 0 | 26 | 0 | 43.37 | 16.63 | 38% |
| 8 | Poultry Shelter | 26 | 0 | 25 | 0 | 65.82 | 63.59 | 97% |
| 9 | Construction of NADEP/Vermi Compost Pit | 25 | 0 | 11 | 14 | 5.38 | 3.50 | 65% |
| 10 | Construction of Percolation Tank | 22 | 0 | 4 | 8 | 76.68 | 75.32 | 98% |
| 11 | Construction of Well | 20 | 0 | 16 | 0 | 34.36 | 24.14 | 70% |
| 12 | Construction of Recharge Pits | 18 | 0 | 7 | 1 | 3.79 | 3.42 | 90% |
| 13 | Construction of Road and Culvert | 12 | 1 | 10 | 1 | 94.44 | 70.86 | 75% |
| 14 | Construction of Trench | 10 | 0 | 9 | 0 | 1.16 | 1.14 | 98% |
| 15 | Constr of Cement Concrete Roads | 10 | 0 | 7 | 3 | 12.97 | 6.88 | 53% |
| 16 | Constr of Gabion | 9 | 0 | 3 | 5 | 7.39 | 7.06 | 96% |
| 17 | Repair & maint of Pond/ Tank | 8 | 0 | 3 | 2 | 55.38 | 37.18 | 67% |
| 18 | Construction of Tank | 8 | 0 | 5 | 2 | 34.70 | 29.59 | 85% |
| 19 | Well Recharge | 5 | 0 | 0 | 0 | 1.29 | 0.99 | 77% |
| 20 | Cattle Shed | 2 | 0 | 0 | 0 | 1.24 | 0.00 | 0% |
| 21 | Solid and Liquid Waste Management | 2 | 1 | 1 | 0 | 2.32 | 0.99 | 43% |
| 22 | Constr of Kitchen Shed | 2 | 0 | 1 | 1 | 8.50 | 4.25 | 50% |
| 23 | Roof Water Harvesting on gov/panchayat bldg | 2 | 0 | 2 | 0 | 0.44 | 0.35 | 80% |
| 24 | Constr of Food Grain storage | 1 | 1 | 0 | 0 | 3.82 | 3.52 | 92% |
| 25 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 5.00 | 4.98 | 100% |
| 26 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 4.01 | 1.10 | 27% |
| 27 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.45 | 0.45 | 100% |
| 28 | Underground Dyke for Ground Water Recharge | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 29 | Construction of Play field | 1 | 0 | 0 | 0 | 3.20 | 0.00 | 0% |
| 30 | Boulder Check/Gully Plug | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 31 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 32 | Construction of Embankment | 1 | 1 | 0 | 0 | 14.16 | 0.02 | 0% |
| 33 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 5.20 | 1.19 | 23% |
| Total | 739 | 52 | 483 | 87 | 772.28 | 588.49 |