| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 267 | 11 | 209 | 0 | 48.74 | 42.12 | 86% |
| 2 | Constr of Cement Concrete Roads | 32 | 2 | 21 | 6 | 32.58 | 17.36 | 53% |
| 3 | Land Development | 26 | 0 | 18 | 4 | 8.84 | 5.73 | 65% |
| 4 | Construction of Well | 16 | 0 | 8 | 4 | 26.48 | 17.94 | 68% |
| 5 | Plantation | 13 | 3 | 5 | 2 | 32.08 | 10.10 | 32% |
| 6 | Construction of Check Dam/Stop Dam | 11 | 0 | 8 | 0 | 17.90 | 8.45 | 47% |
| 7 | Construction of NADEP/Vermi Compost Pit | 9 | 1 | 5 | 2 | 1.34 | 1.03 | 77% |
| 8 | Well Recharge | 7 | 0 | 3 | 2 | 8.21 | 3.64 | 44% |
| 9 | Construction of Bund | 6 | 0 | 1 | 3 | 2.42 | 0.26 | 11% |
| 10 | Construction of Road and Culvert | 6 | 0 | 6 | 0 | 18.01 | 11.69 | 65% |
| 11 | Roof Water Harvesting on gov/panchayat bldg | 5 | 0 | 0 | 5 | 0.28 | 0.00 | 0% |
| 12 | Farm Pond | 4 | 0 | 1 | 0 | 4.94 | 2.17 | 44% |
| 13 | Repair & maint of Pond/ Tank | 3 | 1 | 0 | 2 | 2.64 | 0.63 | 24% |
| 14 | Construction of Trench | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 15 | Community Sanitary Complex | 2 | 0 | 0 | 2 | 1.05 | 0.00 | 0% |
| 16 | Constr of Aganwadi | 2 | 0 | 1 | 1 | 4.19 | 0.79 | 19% |
| 17 | Constr of GP Bhawan | 2 | 0 | 2 | 0 | 16.35 | 10.30 | 63% |
| 18 | Culvert | 2 | 0 | 2 | 0 | 0.30 | 0.14 | 46% |
| 19 | Repair & Maint of Bund | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 20 | Solid and Liquid Waste Management | 1 | 1 | 0 | 0 | 1.05 | 0.29 | 27% |
| 21 | Bio-Fertilizer | 1 | 0 | 0 | 0 | 0.53 | 0.00 | 0% |
| 22 | Construction of Tank | 1 | 0 | 1 | 0 | 5.00 | 4.31 | 86% |
| 23 | Construction of Recharge Pits | 1 | 0 | 0 | 1 | 0.30 | 0.00 | 0% |
| 24 | Cattle Shed | 1 | 0 | 0 | 0 | 0.53 | 0.00 | 0% |
| 25 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 26 | Repair & Maint of Community infrastructure | 1 | 0 | 1 | 0 | 0.25 | 0.06 | 26% |
| 27 | Construction of Play field | 1 | 0 | 0 | 1 | 1.15 | 0.00 | 0% |
| 28 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 3.35 | 1.90 | 57% |
| 29 | Constr of Gabion | 1 | 0 | 1 | 0 | 3.35 | 1.67 | 50% |
| 30 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 0 | 0 | 0.53 | 0.00 | 0% |
| 31 | Construction of Village Haats | 1 | 0 | 1 | 0 | 0.35 | 0.35 | 100% |
| Total | 429 | 19 | 295 | 38 | 242.73 | 140.94 |