| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 154 | 37 | 101 | 0 | 0.33 | 0.30 | 91% |
| 2 | Plantation | 49 | 17 | 8 | 9 | 1.35 | 0.35 | 26% |
| 3 | Constr of Cement Concrete Roads | 21 | 0 | 14 | 0 | 0.13 | 0.13 | 96% |
| 4 | Construction of Toilets | 10 | 0 | 9 | 0 | 0.01 | 0.01 | 62% |
| 5 | Land Development | 10 | 0 | 1 | 3 | 0.07 | 0.00 | 5% |
| 6 | Repair & maint of Pond/ Tank | 9 | 0 | 2 | 6 | 0.08 | 0.05 | 69% |
| 7 | Construction of Well | 9 | 0 | 1 | 8 | 0.09 | 0.02 | 28% |
| 8 | Boulder Check/Gully Plug | 8 | 0 | 0 | 8 | 0.03 | 0.00 | 0% |
| 9 | Well Recharge | 8 | 0 | 0 | 6 | 0.01 | 0.00 | 1% |
| 10 | Construction of Tank | 6 | 1 | 0 | 4 | 0.40 | 0.08 | 19% |
| 11 | Construction of Trench | 5 | 0 | 0 | 4 | 0.00 | 0.00 | 0% |
| 12 | Roof Water Harvesting on gov/panchayat bldg | 4 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 13 | Construction of Recharge Pits | 4 | 0 | 0 | 3 | 0.01 | 0.00 | 1% |
| 14 | Repair & maint of Percolation Tank | 4 | 0 | 0 | 4 | 0.00 | 0.00 | 0% |
| 15 | Construction of Crematorium | 3 | 0 | 3 | 0 | 0.06 | 0.05 | 95% |
| 16 | Constr of Gabion | 3 | 1 | 1 | 0 | 0.14 | 0.04 | 29% |
| 17 | Constr of Aganwadi | 3 | 1 | 0 | 2 | 0.02 | 0.00 | 19% |
| 18 | Construction of Check Dam/Stop Dam | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 19 | Construction of Canal | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Construction of building/workshed for SHG | 2 | 0 | 2 | 0 | 0.04 | 0.03 | 96% |
| 21 | Construction of Road and Culvert | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 22 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.01 | 0.00 | 72% |
| 23 | Repair & maint of Water Harvesting Structures | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 24 | Construction of Play field | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 25 | Cattle Shed | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 26 | Construction of Spur | 1 | 0 | 0 | 1 | 0.05 | 0.00 | 0% |
| 27 | Terracing | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 28 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 324 | 57 | 143 | 67 | 2.82 | 1.08 |