| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 453 | 0 | 451 | 1 | 0.80 | 0.77 | 96% |
| 2 | Construction of Well | 104 | 1 | 72 | 6 | 1.34 | 1.08 | 80% |
| 3 | Plantation | 87 | 0 | 62 | 5 | 1.49 | 0.39 | 26% |
| 4 | Construction of Toilets | 46 | 0 | 40 | 3 | 0.06 | 0.05 | 85% |
| 5 | Farm Pond | 41 | 1 | 29 | 5 | 0.92 | 0.68 | 74% |
| 6 | Construction of Bund | 23 | 0 | 16 | 1 | 0.07 | 0.02 | 26% |
| 7 | Construction of Road and Culvert | 15 | 0 | 9 | 1 | 0.81 | 0.75 | 93% |
| 8 | Construction of Recharge Pits | 11 | 0 | 0 | 0 | 0.03 | 0.02 | 90% |
| 9 | Constr of Cement Concrete Roads | 9 | 0 | 6 | 1 | 0.11 | 0.04 | 38% |
| 10 | Construction of Check Dam/Stop Dam | 6 | 0 | 4 | 0 | 0.32 | 0.32 | 102% |
| 11 | Construction of Tank | 3 | 1 | 0 | 2 | 0.13 | 0.11 | 89% |
| 12 | Construction of NADEP/Vermi Compost Pit | 2 | 0 | 0 | 2 | 0.01 | 0.00 | 0% |
| 13 | Construction of Percolation Tank | 2 | 0 | 2 | 0 | 0.00 | 0.00 | 1% |
| 14 | Construction of Play field | 2 | 0 | 2 | 0 | 0.04 | 0.00 | 0% |
| 15 | Renovation of traditional water bodies | 2 | 0 | 1 | 0 | 0.01 | 0.00 | 0% |
| 16 | Repair & maint of Pond/ Tank | 2 | 0 | 1 | 1 | 0.24 | 0.07 | 29% |
| 17 | Constr of Aganwadi | 2 | 0 | 2 | 0 | 0.04 | 0.04 | 103% |
| 18 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 95% |
| 19 | Repair & maint of Water Harvesting Structures | 1 | 0 | 1 | 0 | 0.05 | 0.05 | 92% |
| 20 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 0.05 | 0.03 | 52% |
| 21 | Construction of Crematorium | 1 | 0 | 1 | 0 | 0.02 | 0.02 | 100% |
| 22 | Constr of Gabion | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 815 | 3 | 701 | 28 | 6.53 | 4.44 |