| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 633 | 139 | 355 | 2 | 1.30 | 0.96 | 74% |
| 2 | Construction of Check Dam/Stop Dam | 72 | 1 | 28 | 3 | 81.13 | 2.21 | 3% |
| 3 | Plantation | 68 | 18 | 28 | 9 | 1.50 | 0.46 | 31% |
| 4 | Construction of Trench | 64 | 0 | 28 | 2 | 1.36 | 0.99 | 73% |
| 5 | Farm Pond | 56 | 0 | 45 | 0 | 0.46 | 0.30 | 65% |
| 6 | Construction of Road and Culvert | 41 | 0 | 23 | 2 | 2.50 | 2.05 | 82% |
| 7 | Constr of Cement Concrete Roads | 32 | 0 | 13 | 3 | 0.33 | 0.22 | 68% |
| 8 | Constr of GP Bhawan | 23 | 1 | 3 | 6 | 0.06 | 0.05 | 75% |
| 9 | Underground Dyke for Ground Water Recharge | 23 | 0 | 17 | 1 | 2.33 | 2.06 | 88% |
| 10 | Construction of Well | 23 | 0 | 22 | 1 | 0.50 | 0.44 | 89% |
| 11 | Cattle Shed | 18 | 0 | 3 | 0 | 0.02 | 0.01 | 63% |
| 12 | Construction of NADEP/Vermi Compost Pit | 17 | 0 | 12 | 2 | 0.02 | 0.02 | 72% |
| 13 | Well Recharge | 12 | 2 | 0 | 0 | 0.22 | 0.08 | 35% |
| 14 | Construction of Percolation Tank | 11 | 0 | 1 | 2 | 0.05 | 0.01 | 13% |
| 15 | Construction of Tank | 9 | 2 | 0 | 3 | 1.03 | 0.00 | 0% |
| 16 | Construction of Bund | 9 | 0 | 2 | 1 | 0.34 | 0.16 | 46% |
| 17 | Construction of Recharge Pits | 7 | 0 | 2 | 0 | 0.18 | 0.17 | 96% |
| 18 | Boulder Check/Gully Plug | 6 | 0 | 3 | 1 | 0.01 | 0.01 | 62% |
| 19 | Solid and Liquid Waste Management | 6 | 0 | 0 | 1 | 0.04 | 0.00 | 0% |
| 20 | Construction of Spur | 4 | 1 | 0 | 0 | 0.06 | 0.03 | 55% |
| 21 | Construction of Toilets | 4 | 0 | 1 | 0 | 0.00 | 0.00 | 96% |
| 22 | Land Development | 4 | 0 | 0 | 1 | 0.06 | 0.01 | 22% |
| 23 | Other Works | 3 | 0 | 2 | 0 | 0.00 | 0.00 | 48% |
| 24 | Culvert | 3 | 0 | 1 | 0 | 0.43 | 0.17 | 40% |
| 25 | Repair & Maint of Community infrastructure | 3 | 0 | 1 | 0 | 0.02 | 0.02 | 99% |
| 26 | Construction of Crematorium | 2 | 0 | 1 | 0 | 0.04 | 0.02 | 51% |
| 27 | Repair & maint of Water Harvesting Structures | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 28 | Repair & maint of Percolation Tank | 1 | 0 | 1 | 0 | 0.05 | 0.04 | 75% |
| 29 | Repair & Maint of Bund | 1 | 0 | 1 | 0 | 0.01 | 0.01 | 78% |
| 30 | Terracing | 1 | 0 | 0 | 1 | 0.01 | 0.00 | 0% |
| 31 | Constr of Gabion | 1 | 0 | 1 | 0 | 0.07 | 0.07 | 96% |
| 32 | Construction of Play field | 1 | 0 | 1 | 0 | 0.04 | 0.00 | 0% |
| Total | 1,159 | 164 | 595 | 41 | 94.17 | 10.56 |