MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Overall

Rollup last refreshed: 2026-10-18 06:53:07.800224 · figures are real, from vg_work_summary_rollup
to
to
Reset filters
Total works
43
All statuses · all years
Approved
6
14% of total
Completed
19
44.2% of total
New
3
7% of total
Ongoing
15
34.9% of total
Sanctioned
₹53.89 L
Pure scheme basis
Expenditure %
0.8%
₹45,800 of ₹53.89 L

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Total works Ongoing Completed Closed Sanctioned Expenditure Exp. %
1 Rural Housing 20 0 19 0 4.73 0.00
0%
2 Plantation 11 7 0 0 29.89 0.45
2%
3 Farm Pond 5 1 0 0 4.43 0.00
0%
4 Construction of Well 2 2 0 0 6.41 0.00
0%
5 Boulder Check/Gully Plug 1 1 0 0 0.17 0.00
0%
6 Construction of Trench 1 1 0 0 1.67 0.00
0%
7 Constr of Cement Concrete Roads 1 1 0 0 1.91 0.01
0%
8 Constr of Compound wall 1 1 0 0 3.57 0.00
0%
9 Construction of Tank 1 1 0 0 1.11 0.00
0%
Total 43 15 19 0 53.89 0.46
All 9 rows (zero-value rows hidden) ⇩ Export to Excel