| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 245 | 17 | 205 | 0 | 54.15 | 45.26 | 84% |
| 2 | Plantation | 28 | 3 | 19 | 5 | 29.15 | 8.80 | 30% |
| 3 | Construction of Bund | 28 | 0 | 14 | 3 | 10.82 | 8.78 | 81% |
| 4 | Construction of Toilets | 24 | 0 | 20 | 2 | 4.80 | 4.65 | 97% |
| 5 | Construction of Well | 17 | 0 | 0 | 1 | 4.45 | 0.00 | 0% |
| 6 | Constr of Cement Concrete Roads | 16 | 1 | 12 | 0 | 12.48 | 11.89 | 95% |
| 7 | Construction of Road and Culvert | 16 | 0 | 16 | 0 | 88.36 | 69.86 | 79% |
| 8 | Farm Pond | 14 | 0 | 9 | 1 | 16.73 | 11.35 | 68% |
| 9 | Solid and Liquid Waste Management | 9 | 0 | 7 | 2 | 0.77 | 0.25 | 33% |
| 10 | Construction of Trench | 6 | 0 | 6 | 0 | 13.11 | 9.24 | 71% |
| 11 | Construction of Recharge Pits | 4 | 0 | 1 | 2 | 0.55 | 0.12 | 21% |
| 12 | Construction of Check Dam/Stop Dam | 4 | 0 | 3 | 0 | 7.96 | 3.70 | 47% |
| 13 | Roof Water Harvesting on gov/panchayat bldg | 3 | 0 | 3 | 0 | 0.72 | 0.68 | 94% |
| 14 | Construction of NADEP/Vermi Compost Pit | 3 | 0 | 3 | 0 | 0.40 | 0.40 | 100% |
| 15 | Land Development | 3 | 0 | 3 | 0 | 8.35 | 8.18 | 98% |
| 16 | Community Sanitary Complex | 2 | 0 | 1 | 1 | 0.94 | 0.47 | 50% |
| 17 | Works for Flood Control and Protection | 2 | 1 | 0 | 1 | 12.00 | 11.31 | 94% |
| 18 | Well Recharge | 2 | 0 | 0 | 1 | 0.25 | 0.25 | 99% |
| 19 | Construction of Tank | 1 | 0 | 1 | 0 | 1.90 | 1.66 | 88% |
| 20 | Constr of Compound wall | 1 | 0 | 1 | 0 | 1.07 | 1.07 | 100% |
| 21 | Construction of Crematorium | 1 | 0 | 1 | 0 | 1.80 | 1.74 | 97% |
| 22 | Construction of Other Community Building/Assets | 1 | 0 | 1 | 0 | 3.50 | 3.47 | 99% |
| 23 | Boulder Check/Gully Plug | 1 | 0 | 1 | 0 | 0.37 | 0.16 | 44% |
| Total | 431 | 22 | 327 | 19 | 274.59 | 203.30 |