| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 190 | 33 | 119 | 0 | 39.73 | 26.71 | 67% |
| 2 | Construction of Bund | 48 | 0 | 32 | 11 | 17.01 | 14.00 | 82% |
| 3 | Construction of Toilets | 17 | 0 | 17 | 0 | 2.04 | 2.01 | 99% |
| 4 | Construction of Road and Culvert | 15 | 0 | 10 | 0 | 61.76 | 36.97 | 60% |
| 5 | Farm Pond | 10 | 1 | 3 | 1 | 4.89 | 3.62 | 74% |
| 6 | Construction of NADEP/Vermi Compost Pit | 10 | 6 | 0 | 4 | 1.12 | 0.04 | 4% |
| 7 | Constr of Cement Concrete Roads | 9 | 0 | 7 | 0 | 12.20 | 11.07 | 91% |
| 8 | Plantation | 7 | 4 | 2 | 0 | 30.22 | 4.22 | 14% |
| 9 | Construction of Tank | 7 | 1 | 4 | 2 | 6.87 | 2.89 | 42% |
| 10 | Solid and Liquid Waste Management | 5 | 0 | 3 | 2 | 0.82 | 0.46 | 56% |
| 11 | Well Recharge | 4 | 0 | 2 | 1 | 0.52 | 0.27 | 53% |
| 12 | Construction of Well | 4 | 0 | 3 | 1 | 2.07 | 2.66 | 129% |
| 13 | Construction of Trench | 3 | 0 | 2 | 0 | 3.69 | 3.23 | 88% |
| 14 | Construction of Recharge Pits | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 15 | Land Development | 2 | 0 | 1 | 0 | 4.52 | 4.21 | 93% |
| 16 | Construction of Crematorium | 2 | 0 | 1 | 0 | 15.24 | 0.25 | 2% |
| 17 | Constr of Compound wall | 2 | 1 | 0 | 1 | 13.54 | 12.62 | 93% |
| 18 | Construction of Play field | 1 | 0 | 1 | 0 | 3.53 | 2.92 | 83% |
| 19 | Construction of Check Dam/Stop Dam | 1 | 1 | 0 | 0 | 27.64 | 0.01 | 0% |
| 20 | Constr of Aganwadi | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 340 | 47 | 207 | 24 | 247.41 | 128.19 |