| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 5,303 | 2,981 | 170 | 0 | 12.45 | 0.20 | 2% |
| 2 | Plantation | 1,675 | 1,299 | 0 | 0 | 48.83 | 0.13 | 0% |
| 3 | Constr of Cement Concrete Roads | 329 | 125 | 0 | 0 | 1.67 | 0.00 | 0% |
| 4 | Farm Pond | 325 | 137 | 0 | 0 | 5.39 | 0.00 | 0% |
| 5 | Well Recharge | 288 | 17 | 0 | 0 | 0.63 | 0.00 | 0% |
| 6 | Solid and Liquid Waste Management | 237 | 102 | 3 | 0 | 1.47 | 0.01 | 1% |
| 7 | Construction of Recharge Pits | 196 | 48 | 0 | 0 | 0.55 | 0.00 | 0% |
| 8 | Roof Water Harvesting on gov/panchayat bldg | 176 | 32 | 0 | 0 | 0.36 | 0.00 | 0% |
| 9 | Construction of Check Dam/Stop Dam | 133 | 29 | 0 | 0 | 2.14 | 0.00 | 0% |
| 10 | Construction of Well | 94 | 54 | 0 | 0 | 1.65 | 0.00 | 0% |
| 11 | Community Sanitary Complex | 90 | 83 | 0 | 0 | 0.97 | 0.00 | 0% |
| 12 | Cattle Shed | 82 | 77 | 0 | 0 | 3.01 | 0.01 | 0% |
| 13 | Construction of Trench | 76 | 22 | 0 | 0 | 0.89 | 0.00 | 0% |
| 14 | Construction of Road and Culvert | 76 | 48 | 0 | 0 | 6.98 | 0.00 | 0% |
| 15 | Construction of NADEP/Vermi Compost Pit | 69 | 47 | 0 | 0 | 0.25 | 0.00 | 0% |
| 16 | Construction of Tank | 64 | 17 | 0 | 1 | 1.58 | 0.00 | 0% |
| 17 | Repair & maint of Pond/ Tank | 46 | 34 | 0 | 0 | 1.29 | 0.00 | 0% |
| 18 | Constr of Aganwadi | 39 | 36 | 0 | 0 | 1.51 | 0.00 | 0% |
| 19 | Land Development | 25 | 20 | 0 | 0 | 1.07 | 0.00 | 0% |
| 20 | Construction of Crematorium | 24 | 17 | 0 | 0 | 0.50 | 0.00 | 0% |
| 21 | Constr of Compound wall | 24 | 18 | 0 | 0 | 0.31 | 0.00 | 0% |
| 22 | Goat Shelter | 22 | 19 | 0 | 0 | 0.10 | 0.00 | 0% |
| 23 | Construction of Percolation Tank | 21 | 12 | 0 | 0 | 0.50 | 0.00 | 0% |
| 24 | Boulder Check/Gully Plug | 21 | 2 | 0 | 0 | 0.02 | 0.00 | 0% |
| 25 | Poultry Shelter | 15 | 13 | 0 | 0 | 0.08 | 0.00 | 0% |
| 26 | Construction of Toilets | 14 | 8 | 0 | 0 | 0.05 | 0.00 | 0% |
| 27 | Terracing | 12 | 5 | 0 | 0 | 0.09 | 0.00 | 3% |
| 28 | Constr of GP Bhawan | 8 | 8 | 0 | 0 | 0.55 | 0.00 | 0% |
| 29 | Culvert | 8 | 3 | 0 | 0 | 0.06 | 0.00 | 0% |
| 30 | Repair & Maint of Community infrastructure | 7 | 5 | 0 | 0 | 0.04 | 0.00 | 0% |
| 31 | Construction of building/workshed for SHG | 5 | 5 | 0 | 0 | 0.21 | 0.00 | 0% |
| 32 | Repair & maint of Road | 4 | 3 | 0 | 0 | 0.26 | 0.00 | 0% |
| 33 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 4 | 1 | 0 | 0 | 0.00 | 0.00 | 0% |
| 34 | Other Works | 4 | 2 | 0 | 0 | 0.06 | 0.00 | 0% |
| 35 | Construction of Play field | 4 | 3 | 0 | 0 | 0.16 | 0.00 | 0% |
| 36 | Repair & Maint of Check Dam/Stop Dam | 4 | 3 | 0 | 0 | 0.05 | 0.00 | 0% |
| 37 | Constr of Kitchen Shed | 3 | 3 | 0 | 0 | 0.01 | 0.00 | 0% |
| 38 | Bio-gas plant | 3 | 0 | 0 | 0 | 0.03 | 0.00 | 0% |
| 39 | (uncategorised) | 3 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 40 | Works for Flood Control and Protection | 2 | 0 | 0 | 0 | 0.01 | 0.00 | 0% |
| 41 | Constr of Food Grain storage | 2 | 1 | 0 | 0 | 0.15 | 0.00 | 0% |
| 42 | Construction of Bund | 2 | 2 | 0 | 0 | 0.47 | 0.00 | 0% |
| 43 | Construction of Canal | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 44 | Construction of Other Community Building/Assets | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 45 | Repair & maint of Water Harvesting Structures | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 46 | Repair & maint of Percolation Tank | 1 | 1 | 0 | 0 | 0.03 | 0.00 | 0% |
| 47 | Construction of Spur | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 48 | Constr of Gabion | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 49 | Grass Land Development | 1 | 1 | 0 | 0 | 0.08 | 0.00 | 0% |
| Total | 9,546 | 5,343 | 173 | 1 | 96.51 | 0.36 |