| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 291 | 7 | 261 | 0 | 51.78 | 44.75 | 86% |
| 2 | Construction of Well | 51 | 0 | 29 | 6 | 91.45 | 65.31 | 71% |
| 3 | Constr of Cement Concrete Roads | 29 | 0 | 24 | 3 | 30.54 | 17.87 | 59% |
| 4 | Construction of Road and Culvert | 29 | 0 | 10 | 7 | 87.75 | 40.01 | 46% |
| 5 | Construction of Toilets | 27 | 0 | 0 | 27 | 3.24 | 0.00 | 0% |
| 6 | Cattle Shed | 18 | 0 | 9 | 0 | 11.24 | 6.22 | 55% |
| 7 | Land Development | 17 | 0 | 6 | 7 | 13.21 | 8.80 | 67% |
| 8 | Construction of Check Dam/Stop Dam | 16 | 0 | 15 | 1 | 17.95 | 13.16 | 73% |
| 9 | Plantation | 14 | 1 | 6 | 2 | 20.66 | 0.86 | 4% |
| 10 | Well Recharge | 9 | 0 | 7 | 0 | 2.07 | 1.73 | 84% |
| 11 | Construction of Recharge Pits | 6 | 0 | 2 | 3 | 0.42 | 0.10 | 24% |
| 12 | Constr of Aganwadi | 5 | 0 | 2 | 1 | 9.00 | 3.78 | 42% |
| 13 | Farm Pond | 5 | 0 | 4 | 0 | 11.97 | 6.58 | 55% |
| 14 | Construction of Play field | 4 | 0 | 0 | 4 | 2.96 | 0.00 | 0% |
| 15 | Repair & maint of Pond/ Tank | 4 | 0 | 2 | 2 | 10.80 | 10.17 | 94% |
| 16 | Solid and Liquid Waste Management | 4 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 17 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 3 | 0 | 1 | 2 | 1.80 | 1.70 | 94% |
| 18 | Construction of Crematorium | 3 | 0 | 1 | 1 | 3.99 | 2.19 | 55% |
| 19 | Construction of Percolation Tank | 3 | 1 | 0 | 1 | 9.80 | 2.88 | 29% |
| 20 | Renovation of traditional water bodies | 1 | 0 | 0 | 1 | 1.07 | 0.00 | 0% |
| 21 | Construction of Trench | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 22 | Terracing | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 23 | Constr of Compound wall | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 24 | Works for Flood Control and Protection | 1 | 0 | 0 | 0 | 13.14 | 3.56 | 27% |
| Total | 543 | 9 | 379 | 73 | 394.85 | 229.68 |