| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 490 | 12 | 422 | 0 | 92.87 | 76.71 | 83% |
| 2 | Construction of Toilets | 254 | 0 | 209 | 0 | 20.94 | 13.50 | 65% |
| 3 | Construction of Check Dam/Stop Dam | 80 | 0 | 72 | 8 | 59.49 | 42.06 | 71% |
| 4 | Constr of Cement Concrete Roads | 36 | 0 | 35 | 0 | 38.36 | 36.13 | 94% |
| 5 | Constr of Gabion | 30 | 0 | 30 | 0 | 31.03 | 24.25 | 78% |
| 6 | Plantation | 20 | 8 | 6 | 1 | 30.15 | 6.46 | 21% |
| 7 | Farm Pond | 17 | 0 | 10 | 7 | 27.04 | 6.23 | 23% |
| 8 | Land Development | 16 | 0 | 15 | 1 | 13.39 | 7.37 | 55% |
| 9 | Construction of NADEP/Vermi Compost Pit | 14 | 0 | 3 | 11 | 0.85 | 0.03 | 3% |
| 10 | Construction of Road and Culvert | 12 | 0 | 11 | 1 | 71.72 | 51.84 | 72% |
| 11 | Underground Dyke for Ground Water Recharge | 10 | 0 | 0 | 10 | 0.98 | 0.00 | 0% |
| 12 | Construction of Trench | 7 | 0 | 7 | 0 | 19.13 | 16.16 | 85% |
| 13 | Constr of Kitchen Shed | 7 | 0 | 3 | 4 | 1.13 | 0.51 | 46% |
| 14 | Well Recharge | 7 | 0 | 4 | 0 | 15.44 | 12.85 | 83% |
| 15 | Construction of Well | 6 | 0 | 3 | 3 | 13.85 | 5.07 | 37% |
| 16 | Construction of Recharge Pits | 6 | 0 | 0 | 6 | 0.85 | 0.00 | 0% |
| 17 | Solid and Liquid Waste Management | 5 | 0 | 5 | 0 | 2.29 | 1.64 | 72% |
| 18 | Repair & maint of Water Harvesting Structures | 4 | 0 | 2 | 2 | 4.46 | 3.94 | 88% |
| 19 | Construction of Bund | 4 | 0 | 3 | 0 | 1.13 | 1.03 | 91% |
| 20 | Construction of Tank | 4 | 0 | 3 | 1 | 17.47 | 16.18 | 93% |
| 21 | Roof Water Harvesting on gov/panchayat bldg | 4 | 0 | 4 | 0 | 0.89 | 0.06 | 7% |
| 22 | Construction of Crematorium | 2 | 0 | 2 | 0 | 1.97 | 1.64 | 83% |
| 23 | Works for Flood Control and Protection | 1 | 0 | 1 | 0 | 4.20 | 1.33 | 32% |
| 24 | Construction of building/workshed for SHG | 1 | 1 | 0 | 0 | 9.86 | 8.48 | 86% |
| 25 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 1.99 | 1.57 | 79% |
| 26 | Construction of Play field | 1 | 0 | 1 | 0 | 0.00 | 0.49 | 0% |
| 27 | Repair & maint of Road | 1 | 0 | 1 | 0 | 0.49 | 0.46 | 94% |
| 28 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.44 | 0.42 | 95% |
| Total | 1,041 | 21 | 854 | 55 | 482.39 | 336.43 |