| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 279 | 11 | 264 | 0 | 0.49 | 0.46 | 93% |
| 2 | Construction of Check Dam/Stop Dam | 29 | 0 | 24 | 0 | 0.77 | 0.68 | 89% |
| 3 | Constr of Cement Concrete Roads | 29 | 1 | 26 | 1 | 0.36 | 0.32 | 88% |
| 4 | Farm Pond | 27 | 3 | 13 | 5 | 0.42 | 0.20 | 47% |
| 5 | Construction of Tank | 24 | 1 | 13 | 8 | 0.58 | 0.24 | 42% |
| 6 | Land Development | 18 | 0 | 14 | 2 | 0.13 | 0.06 | 50% |
| 7 | Construction of Road and Culvert | 11 | 0 | 11 | 0 | 1.03 | 0.81 | 78% |
| 8 | Construction of Percolation Tank | 10 | 0 | 10 | 0 | 0.42 | 0.30 | 72% |
| 9 | Constr of Gabion | 8 | 0 | 8 | 0 | 0.13 | 0.05 | 42% |
| 10 | Plantation | 8 | 1 | 2 | 0 | 0.29 | 0.08 | 30% |
| 11 | Construction of Recharge Pits | 7 | 0 | 0 | 7 | 0.01 | 0.00 | 0% |
| 12 | Solid and Liquid Waste Management | 4 | 0 | 2 | 2 | 0.01 | 0.01 | 71% |
| 13 | Culvert | 4 | 0 | 2 | 0 | 0.22 | 0.18 | 82% |
| 14 | Roof Water Harvesting on gov/panchayat bldg | 4 | 0 | 3 | 1 | 0.01 | 0.01 | 87% |
| 15 | Well Recharge | 4 | 0 | 0 | 1 | 0.14 | 0.05 | 40% |
| 16 | Construction of Crematorium | 4 | 0 | 3 | 0 | 0.07 | 0.05 | 74% |
| 17 | Construction of NADEP/Vermi Compost Pit | 4 | 0 | 3 | 1 | 0.00 | 0.00 | 89% |
| 18 | Repair & maint of Road | 4 | 0 | 4 | 0 | 0.02 | 0.01 | 65% |
| 19 | Cattle Shed | 3 | 0 | 1 | 0 | 0.38 | 0.37 | 98% |
| 20 | Construction of Bund | 3 | 0 | 3 | 0 | 0.01 | 0.01 | 87% |
| 21 | Construction of Trench | 3 | 0 | 3 | 0 | 0.07 | 0.04 | 57% |
| 22 | Construction of Toilets | 2 | 0 | 2 | 0 | 0.01 | 0.01 | 59% |
| 23 | Constr of Compound wall | 2 | 0 | 2 | 0 | 0.07 | 0.07 | 91% |
| 24 | Construction of Well | 2 | 0 | 1 | 1 | 0.08 | 0.01 | 16% |
| 25 | Underground Dyke for Ground Water Recharge | 2 | 0 | 2 | 0 | 0.01 | 0.01 | 74% |
| 26 | Grass Land Development | 2 | 0 | 1 | 0 | 0.08 | 0.02 | 26% |
| 27 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 0.03 | 0.03 | 99% |
| 28 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 103% |
| 29 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 0.01 | 0.01 | 98% |
| 30 | Construction of Play field | 1 | 0 | 1 | 0 | 0.02 | 0.01 | 65% |
| 31 | Repair & maint of Water Harvesting Structures | 1 | 0 | 1 | 0 | 0.01 | 0.01 | 82% |
| 32 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 503 | 17 | 422 | 30 | 5.90 | 4.14 |