| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 153 | 7 | 101 | 1 | 29.72 | 18.30 | 62% |
| 2 | Construction of Toilets | 77 | 0 | 14 | 12 | 2.82 | 0.99 | 35% |
| 3 | Constr of Cement Concrete Roads | 33 | 0 | 15 | 9 | 19.37 | 10.70 | 55% |
| 4 | Plantation | 19 | 0 | 4 | 15 | 36.21 | 1.41 | 4% |
| 5 | Construction of Bund | 14 | 0 | 3 | 0 | 1.40 | 0.87 | 62% |
| 6 | Solid and Liquid Waste Management | 13 | 0 | 1 | 12 | 1.82 | 0.75 | 42% |
| 7 | Construction of NADEP/Vermi Compost Pit | 11 | 0 | 5 | 3 | 1.25 | 0.81 | 65% |
| 8 | Construction of Road and Culvert | 10 | 0 | 1 | 0 | 17.30 | 8.61 | 50% |
| 9 | Farm Pond | 6 | 0 | 1 | 2 | 2.23 | 0.64 | 29% |
| 10 | Construction of Crematorium | 6 | 0 | 3 | 1 | 9.01 | 6.53 | 73% |
| 11 | Cattle Shed | 5 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 12 | Land Development | 4 | 0 | 1 | 0 | 0.12 | 0.02 | 20% |
| 13 | Construction of Well | 4 | 0 | 1 | 3 | 3.08 | 0.15 | 5% |
| 14 | Community Sanitary Complex | 4 | 0 | 1 | 2 | 0.88 | 0.26 | 29% |
| 15 | Other Works | 3 | 0 | 3 | 0 | 1.22 | 0.80 | 66% |
| 16 | Construction of Tank | 2 | 0 | 0 | 0 | 4.81 | 1.39 | 29% |
| 17 | Construction of Play field | 2 | 0 | 1 | 1 | 3.53 | 1.17 | 33% |
| 18 | Construction of Recharge Pits | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 19 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 14.48 | 5.63 | 39% |
| 20 | Construction of Trench | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 21 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 0.43 | 0.43 | 100% |
| 22 | Bio-gas plant | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 23 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 1.80 | 1.46 | 81% |
| Total | 372 | 7 | 158 | 62 | 151.49 | 60.93 |