| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 205 | 32 | 157 | 0 | 38.27 | 32.00 | 84% |
| 2 | Land Development | 36 | 0 | 34 | 1 | 9.27 | 5.93 | 64% |
| 3 | Construction of Trench | 31 | 0 | 25 | 4 | 3.22 | 1.40 | 44% |
| 4 | Plantation | 28 | 0 | 20 | 8 | 70.45 | 2.08 | 3% |
| 5 | Construction of NADEP/Vermi Compost Pit | 26 | 2 | 0 | 24 | 4.64 | 0.02 | 1% |
| 6 | Constr of Cement Concrete Roads | 26 | 0 | 13 | 5 | 12.33 | 7.20 | 58% |
| 7 | Construction of Check Dam/Stop Dam | 25 | 0 | 19 | 5 | 65.66 | 31.74 | 48% |
| 8 | Construction of Well | 16 | 1 | 11 | 4 | 23.85 | 11.66 | 49% |
| 9 | Constr of Aganwadi | 14 | 1 | 7 | 4 | 16.07 | 8.99 | 56% |
| 10 | Construction of Tank | 10 | 0 | 6 | 4 | 4.05 | 2.90 | 72% |
| 11 | Well Recharge | 9 | 0 | 0 | 0 | 2.33 | 1.59 | 68% |
| 12 | Farm Pond | 8 | 0 | 3 | 0 | 14.58 | 3.26 | 22% |
| 13 | Constr of GP Bhawan | 8 | 0 | 2 | 6 | 6.68 | 5.18 | 78% |
| 14 | Repair & maint of Pond/ Tank | 6 | 0 | 1 | 5 | 0.11 | 0.07 | 63% |
| 15 | Construction of Percolation Tank | 5 | 0 | 3 | 1 | 5.89 | 1.92 | 33% |
| 16 | Repair & maint of Water Harvesting Structures | 5 | 0 | 1 | 4 | 0.84 | 0.74 | 89% |
| 17 | Construction of Bund | 4 | 0 | 0 | 4 | 1.09 | 0.00 | 0% |
| 18 | Construction of Crematorium | 4 | 0 | 4 | 0 | 2.34 | 0.03 | 1% |
| 19 | Construction of building/workshed for SHG | 4 | 1 | 0 | 3 | 0.36 | 0.02 | 6% |
| 20 | Cattle Shed | 3 | 1 | 2 | 0 | 39.81 | 33.03 | 83% |
| 21 | Construction of Play field | 3 | 0 | 1 | 1 | 8.07 | 1.84 | 23% |
| 22 | Solid and Liquid Waste Management | 2 | 0 | 1 | 0 | 1.66 | 1.15 | 69% |
| 23 | Culvert | 2 | 0 | 1 | 0 | 1.24 | 0.97 | 79% |
| 24 | Construction of Road and Culvert | 1 | 0 | 1 | 0 | 4.26 | 4.18 | 98% |
| 25 | Construction of Recharge Pits | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 26 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 0.79 | 0.80 | 101% |
| 27 | Terracing | 1 | 0 | 1 | 0 | 0.54 | 0.38 | 70% |
| 28 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.44 | 0.38 | 85% |
| 29 | Construction of Toilets | 1 | 0 | 0 | 1 | 0.54 | 0.01 | 2% |
| Total | 486 | 38 | 315 | 85 | 339.39 | 159.46 |