| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 251 | 26 | 166 | 0 | 51.41 | 30.57 | 60% |
| 2 | Constr of Cement Concrete Roads | 38 | 0 | 26 | 7 | 14.39 | 9.81 | 68% |
| 3 | Construction of NADEP/Vermi Compost Pit | 38 | 0 | 24 | 11 | 3.27 | 1.16 | 35% |
| 4 | Land Development | 33 | 0 | 25 | 3 | 13.84 | 4.29 | 31% |
| 5 | Construction of Well | 28 | 0 | 23 | 0 | 27.42 | 14.11 | 52% |
| 6 | Farm Pond | 23 | 0 | 23 | 0 | 39.69 | 18.75 | 47% |
| 7 | Well Recharge | 22 | 0 | 0 | 9 | 4.76 | 2.32 | 49% |
| 8 | Plantation | 20 | 1 | 10 | 5 | 47.92 | 6.55 | 14% |
| 9 | Solid and Liquid Waste Management | 12 | 1 | 3 | 3 | 2.50 | 1.33 | 53% |
| 10 | Construction of Check Dam/Stop Dam | 8 | 0 | 2 | 5 | 21.49 | 4.45 | 21% |
| 11 | Constr of Aganwadi | 5 | 0 | 3 | 2 | 4.16 | 3.78 | 91% |
| 12 | Works for Flood Control and Protection | 4 | 1 | 1 | 2 | 5.72 | 2.20 | 39% |
| 13 | Construction of Recharge Pits | 4 | 0 | 2 | 2 | 0.43 | 0.19 | 45% |
| 14 | Cattle Shed | 4 | 0 | 4 | 0 | 4.09 | 2.80 | 69% |
| 15 | Repair & Maint of Bund | 3 | 0 | 1 | 2 | 0.37 | 0.36 | 95% |
| 16 | Repair & maint of Pond/ Tank | 3 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 17 | Construction of Canal | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 18 | Construction of Percolation Tank | 1 | 0 | 0 | 0 | 1.11 | 0.37 | 34% |
| 19 | Lining of Canal | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Other Works | 1 | 0 | 0 | 1 | 5.98 | 0.00 | 0% |
| 21 | Renovation of Canal | 1 | 0 | 1 | 0 | 0.36 | 0.33 | 91% |
| 22 | Repair & Maint of Canal | 1 | 0 | 1 | 0 | 0.12 | 0.11 | 89% |
| 23 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 1 | 0 | 0.37 | 0.32 | 85% |
| 24 | Repair & maint of Water Harvesting Structures | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 25 | Roof Water Harvesting on gov/panchayat bldg | 1 | 0 | 0 | 0 | 0.38 | 0.00 | 0% |
| 26 | Construction of Bund | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 27 | Constr of GP Bhawan | 1 | 0 | 1 | 0 | 12.82 | 4.52 | 35% |
| 28 | Terracing | 1 | 0 | 1 | 0 | 3.55 | 3.04 | 86% |
| 29 | Constr of Compound wall | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 30 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 31 | Construction of Trench | 1 | 0 | 0 | 0 | 1.05 | 0.00 | 0% |
| 32 | Construction of Road and Culvert | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 33 | Construction of Play field | 1 | 0 | 1 | 0 | 1.87 | 0.02 | 1% |
| Total | 514 | 29 | 319 | 62 | 269.07 | 111.38 |