| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 283 | 21 | 260 | 0 | 49.48 | 45.36 | 92% |
| 2 | Construction of Bund | 32 | 0 | 15 | 10 | 10.10 | 7.75 | 77% |
| 3 | Constr of Cement Concrete Roads | 20 | 0 | 17 | 2 | 7.21 | 6.87 | 95% |
| 4 | Land Development | 18 | 0 | 15 | 1 | 3.62 | 12.03 | 332% |
| 5 | Construction of Road and Culvert | 16 | 0 | 11 | 2 | 56.50 | 62.26 | 110% |
| 6 | Farm Pond | 12 | 0 | 9 | 1 | 10.88 | 2.80 | 26% |
| 7 | Construction of NADEP/Vermi Compost Pit | 12 | 0 | 3 | 2 | 1.25 | 0.03 | 3% |
| 8 | Plantation | 11 | 2 | 4 | 2 | 24.41 | 2.36 | 10% |
| 9 | Construction of Trench | 9 | 0 | 5 | 0 | 39.89 | 29.52 | 74% |
| 10 | Well Recharge | 6 | 0 | 5 | 0 | 0.52 | 0.23 | 44% |
| 11 | Construction of Tank | 5 | 0 | 0 | 0 | 46.84 | 21.70 | 46% |
| 12 | Construction of Check Dam/Stop Dam | 5 | 0 | 3 | 2 | 19.00 | 18.70 | 98% |
| 13 | Solid and Liquid Waste Management | 3 | 0 | 2 | 1 | 1.54 | 0.66 | 43% |
| 14 | Constr of Compound wall | 3 | 0 | 2 | 1 | 0.73 | 0.94 | 129% |
| 15 | Repair & maint of Pond/ Tank | 3 | 0 | 1 | 2 | 1.50 | 0.31 | 21% |
| 16 | Construction of Percolation Tank | 2 | 0 | 1 | 0 | 18.06 | 9.32 | 52% |
| 17 | Construction of Well | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 18 | Culvert | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 19 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 1.80 | 1.40 | 78% |
| 20 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.44 | 0.40 | 91% |
| 21 | Construction of Crematorium | 1 | 0 | 1 | 0 | 1.60 | 1.60 | 100% |
| 22 | Boulder Check/Gully Plug | 1 | 0 | 0 | 0 | 0.12 | 0.00 | 0% |
| 23 | Construction of Play field | 1 | 0 | 1 | 0 | 3.53 | 3.24 | 92% |
| 24 | Bio-Fertilizer | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 449 | 23 | 357 | 28 | 299.04 | 227.46 |