| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 399 | 1 | 396 | 0 | 77.02 | 75.66 | 98% |
| 2 | Farm Pond | 308 | 0 | 265 | 0 | 51.51 | 38.94 | 76% |
| 3 | Construction of Bund | 84 | 0 | 55 | 26 | 44.26 | 22.85 | 52% |
| 4 | Land Development | 41 | 0 | 26 | 12 | 21.02 | 7.52 | 36% |
| 5 | Solid and Liquid Waste Management | 38 | 0 | 28 | 5 | 1.46 | 0.68 | 47% |
| 6 | Constr of Cement Concrete Roads | 33 | 0 | 25 | 5 | 20.22 | 15.55 | 77% |
| 7 | Construction of Toilets | 28 | 0 | 10 | 0 | 1.26 | 0.29 | 23% |
| 8 | Construction of NADEP/Vermi Compost Pit | 26 | 0 | 5 | 21 | 1.22 | 0.13 | 10% |
| 9 | Plantation | 20 | 2 | 10 | 3 | 31.15 | 17.41 | 56% |
| 10 | Cattle Shed | 15 | 0 | 6 | 6 | 11.08 | 5.70 | 52% |
| 11 | Construction of Check Dam/Stop Dam | 13 | 0 | 9 | 3 | 35.41 | 14.35 | 41% |
| 12 | Well Recharge | 11 | 0 | 0 | 9 | 0.00 | 0.00 | 0% |
| 13 | Constr of Gabion | 7 | 0 | 0 | 5 | 5.81 | 0.00 | 0% |
| 14 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 6 | 0 | 2 | 4 | 3.63 | 0.63 | 17% |
| 15 | Constr of Compound wall | 5 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 16 | Terracing | 3 | 0 | 3 | 0 | 2.92 | 2.53 | 86% |
| 17 | Deepening / Desilting of Flood Channels | 3 | 0 | 3 | 0 | 10.00 | 7.26 | 73% |
| 18 | Construction of Recharge Pits | 3 | 0 | 0 | 1 | 0.78 | 0.37 | 48% |
| 19 | Community Sanitary Complex | 3 | 0 | 1 | 1 | 0.44 | 0.40 | 91% |
| 20 | Construction of Road and Culvert | 3 | 0 | 3 | 0 | 7.63 | 3.95 | 52% |
| 21 | Works for Flood Control and Protection | 2 | 0 | 1 | 1 | 9.81 | 2.00 | 20% |
| 22 | Construction of Crematorium | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 23 | Construction of Well | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 24 | Lining of Canal | 2 | 0 | 2 | 0 | 63.11 | 56.90 | 90% |
| 25 | Repair & maint of Water Harvesting Structures | 1 | 0 | 1 | 0 | 4.54 | 3.39 | 75% |
| 26 | Repair & maint of Pond/ Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 27 | Construction of Tank | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 28 | Underground Dyke for Ground Water Recharge | 1 | 0 | 1 | 0 | 6.51 | 5.96 | 92% |
| 29 | Construction of Canal | 1 | 0 | 1 | 0 | 4.82 | 4.32 | 90% |
| 30 | Boulder Check/Gully Plug | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 1,063 | 3 | 853 | 112 | 415.60 | 286.77 |