| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 311 | 0 | 306 | 0 | 0.57 | 0.54 | 95% |
| 2 | Construction of Bund | 280 | 0 | 207 | 68 | 2.45 | 2.04 | 83% |
| 3 | Construction of Check Dam/Stop Dam | 191 | 1 | 182 | 5 | 26.63 | 1.20 | 5% |
| 4 | Farm Pond | 106 | 0 | 85 | 4 | 1.74 | 1.22 | 70% |
| 5 | Solid and Liquid Waste Management | 69 | 13 | 19 | 37 | 0.40 | 0.20 | 49% |
| 6 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 52 | 0 | 41 | 11 | 0.27 | 0.19 | 73% |
| 7 | Plantation | 37 | 18 | 11 | 4 | 0.50 | 0.15 | 30% |
| 8 | Construction of Well | 29 | 0 | 22 | 5 | 0.59 | 0.38 | 65% |
| 9 | Construction of Road and Culvert | 18 | 0 | 8 | 5 | 9.13 | 0.69 | 8% |
| 10 | Repair & maint of Water Harvesting Structures | 14 | 1 | 6 | 7 | 0.63 | 0.44 | 70% |
| 11 | Construction of Recharge Pits | 14 | 0 | 2 | 10 | 0.01 | 0.01 | 40% |
| 12 | Constr of Cement Concrete Roads | 12 | 0 | 7 | 5 | 0.06 | 0.03 | 49% |
| 13 | Construction of NADEP/Vermi Compost Pit | 12 | 0 | 0 | 2 | 0.04 | 0.00 | 0% |
| 14 | Land Development | 10 | 0 | 8 | 0 | 0.42 | 0.27 | 64% |
| 15 | Construction of Trench | 7 | 0 | 6 | 0 | 0.36 | 0.21 | 57% |
| 16 | Well Recharge | 7 | 1 | 2 | 3 | 0.24 | 0.08 | 33% |
| 17 | Other Works | 7 | 1 | 3 | 3 | 0.19 | 0.13 | 70% |
| 18 | Construction of Village Haats | 5 | 0 | 5 | 0 | 0.01 | 0.01 | 99% |
| 19 | Construction of Percolation Tank | 4 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Works for Flood Control and Protection | 4 | 0 | 4 | 0 | 0.16 | 0.09 | 58% |
| 21 | Deepening / Desilting of Flood Channels | 3 | 0 | 0 | 0 | 2.69 | 0.04 | 2% |
| 22 | Construction of Play field | 2 | 0 | 1 | 0 | 0.04 | 0.02 | 49% |
| 23 | Repair & Maint of Community infrastructure | 2 | 1 | 0 | 1 | 0.16 | 0.01 | 7% |
| 24 | Construction of Crematorium | 2 | 0 | 2 | 0 | 0.04 | 0.03 | 80% |
| 25 | Nursery Development | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 26 | Repair & maint of Pond/ Tank | 2 | 0 | 0 | 2 | 0.11 | 0.00 | 0% |
| 27 | Repair & Maint of Bund | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 28 | Construction of Tank | 2 | 0 | 0 | 0 | 0.05 | 0.04 | 73% |
| 29 | Constr of Compound wall | 1 | 0 | 1 | 0 | 0.01 | 0.00 | 12% |
| 30 | Repaire and Maint of NADEP/Vermi Compost Pit | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 31 | Constr of Aganwadi | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 32 | Terracing | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 1,210 | 36 | 928 | 177 | 47.48 | 8.01 |