| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 76 | 1 | 56 | 0 | 17.26 | 15.74 | 91% |
| 2 | Land Development | 58 | 0 | 34 | 11 | 23.52 | 18.16 | 77% |
| 3 | Construction of Toilets | 46 | 0 | 44 | 0 | 3.87 | 3.01 | 78% |
| 4 | Construction of NADEP/Vermi Compost Pit | 28 | 0 | 13 | 10 | 2.83 | 1.92 | 68% |
| 5 | Farm Pond | 26 | 0 | 19 | 0 | 3.35 | 2.49 | 74% |
| 6 | Plantation | 14 | 2 | 9 | 1 | 18.32 | 6.10 | 33% |
| 7 | Constr of Cement Concrete Roads | 13 | 0 | 5 | 3 | 13.90 | 3.11 | 22% |
| 8 | Construction of Check Dam/Stop Dam | 13 | 0 | 11 | 2 | 28.74 | 16.96 | 59% |
| 9 | Construction of Well | 12 | 0 | 4 | 5 | 10.59 | 5.80 | 55% |
| 10 | Construction of Trench | 7 | 1 | 3 | 2 | 10.38 | 3.65 | 35% |
| 11 | Cattle Shed | 6 | 0 | 0 | 4 | 1.36 | 0.00 | 0% |
| 12 | Construction of Bund | 6 | 0 | 2 | 2 | 8.45 | 6.54 | 77% |
| 13 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 6 | 0 | 1 | 3 | 1.51 | 1.10 | 73% |
| 14 | Well Recharge | 6 | 2 | 0 | 0 | 1.04 | 0.52 | 50% |
| 15 | Constr of Compound wall | 4 | 0 | 1 | 2 | 1.04 | 0.48 | 46% |
| 16 | Construction of Road and Culvert | 3 | 0 | 2 | 1 | 9.80 | 4.53 | 46% |
| 17 | Construction of Other Community Building/Assets | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 18 | Repair & Maint of Community infrastructure | 2 | 0 | 1 | 1 | 0.16 | 0.14 | 87% |
| 19 | Construction of Recharge Pits | 2 | 0 | 1 | 0 | 3.24 | 2.41 | 75% |
| 20 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 1.44 | 0.87 | 61% |
| 21 | Works for Flood Control and Protection | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 22 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 1 | 0 | 2.58 | 2.16 | 84% |
| 23 | Repair & maint of Pond/ Tank | 1 | 0 | 1 | 0 | 1.17 | 1.07 | 91% |
| 24 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 1.80 | 1.79 | 100% |
| 25 | Solid and Liquid Waste Management | 1 | 0 | 1 | 0 | 0.20 | 0.14 | 69% |
| 26 | Repair & Maint of Bund | 1 | 0 | 1 | 0 | 4.01 | 2.75 | 69% |
| 27 | Culvert | 1 | 1 | 0 | 0 | 14.88 | 13.56 | 91% |
| 28 | Construction of Crematorium | 1 | 0 | 0 | 0 | 1.80 | 0.00 | 0% |
| 29 | Constr of Kitchen Shed | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 30 | Other Works | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 341 | 7 | 212 | 51 | 187.23 | 115.02 |