| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 363 | 15 | 284 | 1 | 0.77 | 0.58 | 76% |
| 2 | Construction of Bund | 127 | 0 | 88 | 38 | 1.26 | 0.96 | 76% |
| 3 | Land Development | 74 | 0 | 55 | 9 | 0.62 | 0.55 | 89% |
| 4 | Construction of Toilets | 62 | 0 | 52 | 7 | 0.04 | 0.03 | 81% |
| 5 | Construction of Check Dam/Stop Dam | 48 | 0 | 43 | 2 | 1.03 | 0.76 | 74% |
| 6 | Constr of Cement Concrete Roads | 46 | 0 | 14 | 20 | 0.88 | 0.17 | 19% |
| 7 | Plantation | 44 | 6 | 9 | 11 | 0.89 | 0.31 | 35% |
| 8 | Farm Pond | 31 | 0 | 16 | 1 | 0.56 | 0.42 | 75% |
| 9 | Construction of Road and Culvert | 21 | 0 | 16 | 0 | 2.86 | 0.89 | 31% |
| 10 | Solid and Liquid Waste Management | 12 | 0 | 7 | 5 | 0.06 | 0.04 | 69% |
| 11 | Works for Flood Control and Protection | 10 | 0 | 6 | 2 | 0.22 | 0.06 | 27% |
| 12 | Construction of Trench | 6 | 0 | 4 | 1 | 0.14 | 0.14 | 95% |
| 13 | Construction of Tank | 4 | 0 | 3 | 0 | 0.25 | 0.21 | 83% |
| 14 | Construction of Recharge Pits | 3 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 15 | Construction of NADEP/Vermi Compost Pit | 3 | 0 | 1 | 2 | 0.00 | 0.00 | 68% |
| 16 | Repaire and Maint of NADEP/Vermi Compost Pit | 3 | 0 | 2 | 1 | 0.02 | 0.02 | 92% |
| 17 | Construction of Well | 2 | 0 | 2 | 0 | 0.02 | 0.02 | 91% |
| 18 | Construction of Percolation Tank | 2 | 0 | 1 | 0 | 0.04 | 0.04 | 95% |
| 19 | Culvert | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 20 | Well Recharge | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 21 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 99% |
| 22 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 1 | 0 | 0.14 | 0.13 | 89% |
| 23 | Repair & maint of Road | 1 | 0 | 1 | 0 | 0.15 | 0.15 | 97% |
| 24 | Repair & maint of Water Harvesting Structures | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 97% |
| 25 | Roof Water Harvesting on gov/panchayat bldg | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 99% |
| 26 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 0.08 | 0.08 | 106% |
| 27 | Construction of building/workshed for SHG | 1 | 0 | 1 | 0 | 0.06 | 0.05 | 82% |
| 28 | Constr of Aganwadi | 1 | 0 | 0 | 0 | 0.08 | 0.00 | 0% |
| 29 | Lining of Canal | 1 | 0 | 1 | 0 | 0.02 | 0.01 | 87% |
| Total | 874 | 21 | 611 | 100 | 10.21 | 5.62 |