| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 278 | 1 | 275 | 0 | 0.49 | 0.47 | 97% |
| 2 | Land Development | 104 | 0 | 76 | 10 | 0.71 | 0.59 | 82% |
| 3 | Farm Pond | 103 | 0 | 78 | 12 | 2.64 | 2.23 | 85% |
| 4 | Construction of Toilets | 65 | 0 | 46 | 8 | 0.07 | 0.05 | 78% |
| 5 | Construction of Bund | 50 | 0 | 29 | 14 | 0.38 | 0.31 | 82% |
| 6 | Construction of Road and Culvert | 36 | 0 | 15 | 9 | 0.56 | 0.75 | 134% |
| 7 | Cattle Shed | 26 | 0 | 14 | 8 | 0.17 | 0.15 | 85% |
| 8 | Plantation | 23 | 2 | 12 | 2 | 0.37 | 0.11 | 30% |
| 9 | Construction of Check Dam/Stop Dam | 20 | 0 | 14 | 4 | 0.43 | 0.40 | 94% |
| 10 | Constr of Cement Concrete Roads | 17 | 0 | 14 | 1 | 0.10 | 0.11 | 105% |
| 11 | Construction of Well | 13 | 0 | 6 | 6 | 0.17 | 0.08 | 45% |
| 12 | Goat Shelter | 9 | 0 | 5 | 4 | 0.02 | 0.02 | 84% |
| 13 | Poultry Shelter | 9 | 0 | 2 | 5 | 0.02 | 0.01 | 56% |
| 14 | Well Recharge | 9 | 0 | 6 | 0 | 0.02 | 0.02 | 65% |
| 15 | Solid and Liquid Waste Management | 7 | 0 | 6 | 1 | 0.03 | 0.02 | 77% |
| 16 | Repair & maint of Pond/ Tank | 6 | 0 | 3 | 3 | 0.25 | 0.23 | 90% |
| 17 | Culvert | 4 | 0 | 1 | 3 | 0.30 | 0.14 | 47% |
| 18 | Construction of Trench | 3 | 0 | 3 | 0 | 0.03 | 0.03 | 85% |
| 19 | Construction of Percolation Tank | 3 | 0 | 3 | 0 | 0.26 | 0.24 | 94% |
| 20 | Nursery Development | 2 | 0 | 2 | 0 | 0.00 | 0.00 | 34% |
| 21 | Construction of Fish Drying Infrastructure | 2 | 0 | 1 | 1 | 0.03 | 0.02 | 67% |
| 22 | Construction of Recharge Pits | 2 | 0 | 2 | 0 | 0.00 | 0.00 | 100% |
| 23 | Repair & Maint of Bund | 2 | 0 | 2 | 0 | 0.07 | 0.08 | 104% |
| 24 | Construction of Crematorium | 1 | 0 | 1 | 0 | 0.02 | 0.02 | 99% |
| 25 | Renovation of traditional water bodies | 1 | 0 | 1 | 0 | 0.01 | 0.01 | 93% |
| 26 | Construction of Play field | 1 | 0 | 1 | 0 | 0.04 | 0.03 | 79% |
| 27 | Repair & Maint of Canal | 1 | 0 | 1 | 0 | 0.07 | 0.07 | 95% |
| 28 | Construction of NADEP/Vermi Compost Pit | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 99% |
| 29 | Constr of Aganwadi | 1 | 0 | 1 | 0 | 0.05 | 0.05 | 100% |
| 30 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 1 | 0 | 0.05 | 0.05 | 94% |
| 31 | Underground Dyke for Ground Water Recharge | 1 | 0 | 1 | 0 | 0.00 | 0.05 | 0% |
| 32 | Constr of Compound wall | 1 | 0 | 1 | 0 | 0.06 | 0.06 | 100% |
| Total | 802 | 3 | 624 | 91 | 7.44 | 6.39 |