| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 279 | 10 | 266 | 0 | 0.50 | 0.48 | 95% |
| 2 | Land Development | 83 | 0 | 66 | 8 | 1.18 | 0.23 | 19% |
| 3 | Well Recharge | 42 | 8 | 21 | 11 | 0.08 | 0.05 | 68% |
| 4 | Farm Pond | 31 | 1 | 12 | 0 | 0.75 | 0.43 | 57% |
| 5 | Construction of Well | 30 | 4 | 19 | 4 | 0.56 | 0.24 | 42% |
| 6 | Plantation | 23 | 4 | 14 | 0 | 0.70 | 0.12 | 17% |
| 7 | Solid and Liquid Waste Management | 22 | 0 | 1 | 18 | 0.03 | 0.01 | 26% |
| 8 | Construction of Check Dam/Stop Dam | 19 | 0 | 13 | 3 | 0.51 | 0.33 | 64% |
| 9 | Construction of Tank | 13 | 1 | 4 | 2 | 0.70 | 0.46 | 65% |
| 10 | Construction of Road and Culvert | 12 | 0 | 10 | 1 | 0.49 | 0.19 | 39% |
| 11 | Constr of Cement Concrete Roads | 10 | 1 | 5 | 3 | 0.26 | 0.05 | 20% |
| 12 | Construction of NADEP/Vermi Compost Pit | 7 | 0 | 0 | 5 | 0.00 | 0.00 | 0% |
| 13 | Cattle Shed | 7 | 1 | 0 | 5 | 0.01 | 0.00 | 7% |
| 14 | Construction of Bund | 6 | 0 | 3 | 3 | 0.06 | 0.05 | 90% |
| 15 | Constr of Aganwadi | 6 | 0 | 2 | 3 | 0.04 | 0.04 | 99% |
| 16 | Construction of Trench | 6 | 0 | 2 | 0 | 0.12 | 0.01 | 10% |
| 17 | Construction of Toilets | 5 | 0 | 2 | 3 | 0.01 | 0.01 | 97% |
| 18 | Other Works | 5 | 3 | 0 | 2 | 0.03 | 0.01 | 45% |
| 19 | Construction of Play field | 4 | 0 | 2 | 2 | 0.07 | 0.06 | 86% |
| 20 | Repair & maint of Pond/ Tank | 4 | 0 | 2 | 2 | 0.10 | 0.10 | 99% |
| 21 | Construction of Fish Drying Infrastructure | 3 | 0 | 2 | 0 | 0.10 | 0.07 | 68% |
| 22 | Repair & Maint of Community infrastructure | 3 | 0 | 1 | 2 | 0.01 | 0.00 | 22% |
| 23 | Roof Water Harvesting on gov/panchayat bldg | 3 | 0 | 1 | 2 | 0.02 | 0.02 | 94% |
| 24 | Repair & Maint of Bund | 2 | 0 | 1 | 1 | 0.01 | 0.01 | 131% |
| 25 | Construction of Percolation Tank | 2 | 0 | 1 | 1 | 0.02 | 0.02 | 88% |
| 26 | Construction of Recharge Pits | 2 | 0 | 2 | 0 | 0.02 | 0.02 | 134% |
| 27 | Constr of GP Bhawan | 2 | 0 | 0 | 2 | 0.01 | 0.00 | 0% |
| 28 | Construction of Crematorium | 1 | 0 | 1 | 0 | 0.02 | 0.02 | 99% |
| 29 | Underground Dyke for Ground Water Recharge | 1 | 0 | 1 | 0 | 0.03 | 0.01 | 20% |
| 30 | Bio-Fertilizer | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 31 | Community Sanitary Complex | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| Total | 635 | 33 | 454 | 84 | 6.42 | 3.01 |