| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 179 | 18 | 143 | 1 | 0.36 | 0.33 | 92% |
| 2 | Construction of Bund | 35 | 0 | 24 | 7 | 0.17 | 0.05 | 32% |
| 3 | Constr of Cement Concrete Roads | 22 | 1 | 17 | 0 | 1.07 | 0.20 | 19% |
| 4 | Construction of Well | 20 | 0 | 14 | 5 | 0.36 | 0.13 | 36% |
| 5 | Cattle Shed | 19 | 1 | 14 | 1 | 0.99 | 0.46 | 47% |
| 6 | Plantation | 19 | 7 | 7 | 0 | 0.54 | 0.14 | 25% |
| 7 | Construction of Check Dam/Stop Dam | 18 | 0 | 7 | 6 | 0.92 | 0.52 | 57% |
| 8 | Farm Pond | 16 | 0 | 6 | 0 | 0.20 | 0.11 | 56% |
| 9 | Well Recharge | 16 | 0 | 0 | 2 | 0.03 | 0.03 | 85% |
| 10 | Construction of Road and Culvert | 12 | 0 | 11 | 0 | 0.61 | 0.48 | 79% |
| 11 | Construction of Trench | 11 | 0 | 10 | 1 | 0.46 | 0.23 | 51% |
| 12 | Works for Flood Control and Protection | 9 | 0 | 8 | 1 | 0.10 | 0.03 | 33% |
| 13 | Construction of NADEP/Vermi Compost Pit | 7 | 0 | 2 | 5 | 0.00 | 0.00 | 92% |
| 14 | Constr of Gabion | 6 | 0 | 1 | 4 | 0.01 | 0.00 | 1% |
| 15 | Construction of Toilets | 5 | 0 | 4 | 0 | 0.09 | 0.07 | 84% |
| 16 | Boulder Check/Gully Plug | 5 | 0 | 3 | 1 | 0.03 | 0.01 | 32% |
| 17 | Grass Land Development | 5 | 0 | 1 | 2 | 0.08 | 0.00 | 0% |
| 18 | Repair & maint of Pond/ Tank | 4 | 0 | 4 | 0 | 0.08 | 0.05 | 64% |
| 19 | Constr of Compound wall | 3 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 20 | Land Development | 3 | 0 | 1 | 0 | 0.07 | 0.04 | 52% |
| 21 | Renovation of traditional water bodies | 3 | 0 | 2 | 0 | 0.12 | 0.09 | 74% |
| 22 | Constr of GP Bhawan | 2 | 0 | 2 | 0 | 0.00 | 0.00 | 50% |
| 23 | Constr of Kitchen Shed | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 24 | Construction of Tank | 2 | 1 | 0 | 0 | 0.05 | 0.01 | 30% |
| 25 | Repair & maint of Water Harvesting Structures | 2 | 1 | 0 | 0 | 0.01 | 0.00 | 24% |
| 26 | Terracing | 1 | 0 | 1 | 0 | 0.03 | 0.01 | 47% |
| 27 | Construction of Percolation Tank | 1 | 0 | 1 | 0 | 0.03 | 0.01 | 38% |
| 28 | Community Sanitary Complex | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 91% |
| 29 | Construction of Crematorium | 1 | 0 | 0 | 0 | 0.03 | 0.00 | 0% |
| 30 | Construction of Play field | 1 | 0 | 0 | 0 | 0.04 | 0.00 | 0% |
| 31 | Repair & Maint of Check Dam/Stop Dam | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 32 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 432 | 29 | 284 | 40 | 6.48 | 3.02 |